bug, although this was still not quite clear. The problem seems to occur when there is an interrupt during a read cycle. Changing interrupt vectors an

Size: px
Start display at page:

Download "bug, although this was still not quite clear. The problem seems to occur when there is an interrupt during a read cycle. Changing interrupt vectors an"

Transcription

1 Minutes of the ATLAS UK T1 Meeting Present 17 th July 1996 RAL Adam Connors, James Edwards, Eric Eisenhandler, Norman Gee, Tony Gillman, Stephen Hillier, Murrough Landon, Viraj Perera, David Rees, Tara Shah, Alan Watson. Apologies Bob Hatley, Mike Pentney, Richard Staley. Demonstrator Status 1. Status of the TXM Viraj Perera The necessary modifications were being included into the final design, which would then be checked by Giles during his brief return to Rutherford. Kevin Hatton is to replace Giles and will be testing the TXM modules from now on. It was decided to delay the final authorisation for the production of the next batch of TXMs until more testing had been performed on the complete system this may even be after the September test-beam. Major areas still to be tested include the 80 MHz mode, block transfer and long soak tests. 2. Status of the CPM Tony Gillman for Richard Staley On the problem of the slow data transmission from the Serial to Parallel ASICs, Richard had investigated bypassing the PCB lines and just wiring directly from the ASIC pins, separated from the PCB, to the memory elements. The waveforms looked much better and the data was not corrupted. Work had then been carried out at RAL to lift the data output pins from the PCB for all 13 S/P ASICs on one CPM board. That meant lifting almost 200 pins, and proved to be quite difficult. The board was to be sent back to Birmingham for the re-wiring of the data lines to the memory components. The CP ASIC would not be wired up as this is not needed for the current demonstrator program, and it should guarantee better signal transmission to the memories. The other two CPM boards were to have the same treatment in the near future. The time needed for re-wiring each board was estimated as a week, although experience would soon indicate if this was a reasonable expectation. Other than this fix, all three boards were at the same level of modification and all other tested functions were working. Richard had done some preliminary work on the backplane output from the CPM boards using an extender card and was not very happy with the signals, but had had no more time to investigate due to illness. 3. Status of the TCM Tony Gillman for Bob Hatley There were two outstanding problems. Firstly there was the problem observed at the test-beam that the clock frequency switched to a rather unhelpful 14.3 MHz. This was found to be due to interaction between the two different clocks on the board, and was solved temporarily by removing a shaping capacitor on one of the clocks, but a genuine solution must still be found. The second was the interrupt problem, which may now have been tied down to a hardware 1

2 bug, although this was still not quite clear. The problem seems to occur when there is an interrupt during a read cycle. Changing interrupt vectors and priorities was found to make the problem better or worse with no obvious logic. Bob had identified one chip in the VME interface (VME 3000 chip) that was failing to propagate interrupts when the problem occurred, and was attempting to replace it with a custom PLD. Norman had also contacted Lynx for help. 4. Hardware Tests at Birmingham Steve Hillier The final crate had still not been received, as at Rutherford, and perhaps it was time to start making a fuss, or at least checking that the correct fan tray would be sent, since QMW had had a problem with this. It was suggested that a proper test of the J2 connector of the CPM crates should be made, since all the tests so far would have only checked the J1 part of the VME bus. 5. Diagnostic Software Status Tara Shah A new version of the software including more CPM testing and implementing the model for the TXM had been created. This was running at Birmingham and QMW, but hadn't yet been tested with the hardware at Rutherford, since it hadn't been installed as the default version. In fact it wouldn't have worked initially due to a feature relating to the slightly out of date version of tcl/tk being used at Rutherford. The new version had eventually been installed at Rutherford for more thorough testing in the near future. The correct performance of the model had still to be checked and tuned to the exact features of the real TXM. As yet the model results are not being used for comparison in a user friendly way. Dave had given a talk at a software meeting on the model implementation, and on restructuring the diagnostic software in order to simplify its use. It was felt that the software should be restructured before continuing to build models for the other hardware components. 6. DAQ software for August Norman Gee Norman stated that although the DAQ software had, with some effort, managed to cope with the June test-beam, much work was needed to get it up to standard for the next test-beam. Most of the code was essentially ready for the FADC, CPM and TXM, except for the TCM interrupt problem (which may still be hardware) and a bug relating to control of the Peak Finder Override mode in the TXM. The Babar module was `semi-supported' as a CPM this should be changed to keep the module separate from the CPMs. Only a skeleton was in place for the CPM, mostly related to the memory readout. The control of the module was still to be done now Norman had the CPM programming model. With the addition of CPM code and some work on control parameters, it would be possible to start a run, then work would be required to understand the data coming out, and to debug from there. Unfortunately, Norman would be away for three weeks up to almost the start of the test-beam, so Murrough would have to continue the work since he knows the DAQ system well. Steve would help with the CPM programming and start to learn about the DAQ software at the same time. This would cause some logistical problems since the test system is most likely to be located at RAL. Norman would make available a list of other problems that needed work. It was decided not to upgrade to LynxOS 2.4 until after the test-beam. This had been installed at QMW, and the DAQ software compiled with a few modifications, but there was an outstanding problem with EMU. 2

3 7. Ideas for DAQ software for next year Murrough Landon The present run control via menus was unpopular, and Murrough proposed replacing it with a more user-friendly GUI, probably written in tcl/tk. This would be particularly useful for configuring the many cards in the complete system, and also provide an opportunity to clean up the code although it appeared Norman had done much of this already. Other than the extra work involved writing the new interface, there is one major problem. That is the large memory requirement of the X-based program, which might be a problem in an already stretched 16 MByte MVME167. One solution could be to split the interface over two systems, with a simple program running on LynxOS communicating with the tcl/tk application running on a different system. This has the disadvantage of added complexity. Alternatively buying more memory for the 167 might be a simpler solution. Murrough showed some ideas he had already been working on for run control and card configuration. It was thought that this would be a great improvement, but run control from a dumb terminal must be preserved too. General Status and Plans 8. ASIC and MCM Developments Viraj Perera Viraj presented plans for producing an ASIC with many prototype circuits to gain experience for the final ASIC design. This would be submitted to the December Europractice run, and would cost about 3K. Elements included in the ASIC would be test designs for the phase locked delay, 160 MHz and 40 MHz timing calibration logic, 160 Mbit/s transmitter and, if space permits, fast adders and multipliers. Costing constraints mean that the size should be restricted to a mm 2 chip, but if it is felt that some elements should not be left to the next round, then two chips could be submitted. Two chips of the same size would save on testing costs as the same test card could be used. It was felt that some priority should be placed on the adder/multiplier development. Viraj had attended the Cadence course which was useful for some aspects, but had no MCM specific work. There will be no new MCM courses for the version of the package bought by RAL, but hopefully the old documentation can be obtained. Viraj then discussed the possible MCM technology choices and their implications for power dissipation, packaging and chip removability. For tight power constraints, an Aluminium substrate appears to be the best option. Plastic Ball Grid Array (PBGA) is another potentially cheaper choice for MCM packaging. On the AMCC alternative to G-Link, Viraj had established that bare dies could be supplied, even if this is unusual. There is the problem that that are designed to run at 50 MHz +/- 20%, which in principle may be alright for 40 MHz running, but should be checked. Alternatively schemes could be devised to run at them at 50 MHz but not use all of the bandwidth. Timescales for trying out the AMCC option, probably combining this with a first trial of MCM design, were discussed. It may be possible to have an AMCC based link ready for the April test-beam allowing a couple of months for the MCM design. The custom G-Link alternative design that had been discussed in the last meeting would definitely not be ready to be integrated into the demonstrator for April. 3

4 9. BCID Developments David Rees Dave had been working on a more detailed simulation of the CFD algorithm in order to compare performance with digital BCID. This duplicates some of the work done by Jacques Colas, but it is useful for us to have a full understanding of the issue. Dave needed more time to look carefully at the noise and threshold effects and would then write a document summarising the results. 10. BCID paper Norman Gee Copies of Ian's thesis and various figures were now available, John and Norman were undertaking the task of distilling them into the outline of a paper. 11. Simulation status and programme Alan Watson Alan stated that there was still much work to be done to finalise and justify trigger design choices in terms of the physics performance offered by the complete trigger system. He had attempted to list all the parts that still needed work and had categorised them in six areas: ffl Front End Processing and Data Format Assuming digital BCID, the ADC type (8 or 10 bit, 40 or 80 MHz) and dynamic range must be chosen, and the implications of compressed data investigated. The nature of the noise also plays a large part in these decisions. The issue of trigger tower definitions comes under this heading. Simulations so far suggest that summing different detectors across transition regions will be unnecessary, which is good, but should be checked with an up-to-date simulation. Use of the presampler has not been considered yet, and the FCAL trigger tower definition still needs work. ffl e=fl Trigger Although the cluster algorithm itself seems to be stable, the declustering is still a potential problem especially for Level 2. Classification of trigger codes could also be usefully looked at. ffl Jet Trigger Both the cluster definition and the declustering are still undecided. No evidence exists at the moment for a preference for any one algorithm, so more simulation is needed to check that the simpler 0:4 0:4 option is viable. The fact that this proves to work well in existing simulations relies partly on the small jet size predicted by PYTHIA, but how much can this be trusted? ffl Missing E t Trigger A decision on the ffi granularity is still needed, taking into account other factors degrading the resolution. ffl fi/hadron Trigger The exact physics requirements here are still unclear, so it should be considered as of secondary importance, and an algorithm found to fit in with the rest of the architecture. ffl Other Issues This includes issues such as luminosity monitoring, other triggers, such as Sum-E t and the currently unclear problem of beam-halo background. Alan had circulated a long note summarising the current areas of interest in order to prompt a discussion. This had had little response. It was commented that this is an area where help from other institutes could be fruitful. Another idea that should be considered with front-end processing was the effect on the trigger if small signals were let through the system with no BCID processing. 4

5 June test-beam run 12. First look at data Adam Connors Adam had checked that the data transfer through the DAQ seemed to have worked correctly to the bit level. One problem that persisted from previous test-beams was FADC `slipping', which was observed to be the same with the old DAQ chain, and still appeared to happen with the new DAQ. However it was more difficult to be certain about what was happening with the new DAQ, since the TDC stopped working, so cuts on trigger phase relative to the clock could not be made. Adam showed an example with the new DAQ where the FADC had slipped one tick, but the TXM seemed to have the data in the correct time slice. However, he also found examples where the TXM data seemed to have slipped too. This is perfectly understandable given that no attempt was made to adjust TCM delays to time the TXM in correctly. Slightly more puzzling, but perhaps still OK, was an event where the TXM and FADC seemed to have slipped two clock ticks. The data had been copied, and was available in various places Eric had the original tapes. It was stressed that the Babar data should be checked out in the near future. Norman and Eric also had some plots showing the data flowing correctly through the DAQ system. Mike and Bob were at CERN uncabling the system from the old test-beam setup ready for th new run. August/September test-beam run Overall Scenario Tony Gillman Tony showed the SPS schedule which indicated the Tile Calorimeter run starting on 21 st August. In fact they requested a change in schedule meaning they would start on 29 th August and run until 16 th September. The configuration of the detector would be three layers consisting of 0:2m 0:2m towers, the new `Module 0' detector being the middle layer. The detector would be situated in H8B and access would be guaranteed up to 21 st August. It was not clear if there would be significant access after this date. Also Tony was not sure where precisely H8B is, and therefore if perhaps the Level 1 crates need to be moved. The Tile schedule should mean that the detector is complete and in place by 15 th August, but Mike would find out more information during his visit to CERN. Tony then presented his four stage test-beam plan. ffl Stage 1. Cabling to Module `0' and 1994 linear signals must be done. Tony proposed to just use the front layer of Module `0', but sum all layers of the 1994 signals. Sten had been involved with making sure there were sufficient outputs for us to take signals, we should check this has been done for Module `0' it should be OK already for the 1994 modules. Several 40m cables (possibly 80m depending on location) should be laid, and also a couple of optical 80m cables. The initial DAQ system would just consist of the FADC TXM CPM(BaBar) chain in order to set up a simple system which should be well tested before going to CERN. The use of 1994 or Module `0' signals means that we should start to use the TXM lookup tables. ffl Stage 2. Next a second full FADC to CPM chain should be added, and then we would be starting to exercise the backplane. 5

6 ffl Stage 3. Next we can test out the Heidelberg front-end module, if it is available, and use it instead of a TXM. This could be used to make a full third chain meaning the third CPM should be available for use too. Extra software will need to be written to test the Heidelberg module, although as far as the data chain is concerned, it should behave exactly the same as the other TXMs. ffl Stage 4. Finally different data links can be tested. It would be good to try out the VCSEL links which have not been part of a test-beam so far. Tony presented a new schedule of work before and during the test-beam. The CPM again has been delayed due to the time taken in finding a solution to the ASIC problem. Tony also showed the timetable of peoples movements. It was clear that careful planning would be needed to make sure there was enough effort in the right areas in order to be ready for the test-beam. On priorities, it was clear that the backplane and integrating the Heidelberg module were the most important objectives, with the VCSEL testing being less important. 14. Organisation for the test-beam Discussion Steve, as test-beam coordinator, was given a list of jobs that should be seen to over the next few weeks. Important tasks included overseeing the equipment, contacting other groups and making a plan for the manpower at CERN and in the UK. There was also a discussion of how best to do system tests, whether with the diagnostic software, DAQ software or offline with recorded data. Some tests could be done with the diagnostic software, though soak tests are limited to the DAQ system at the moment. Dave would be working more on the model with the idea of being able to perform soak tests via the diagnostic model, but it was clear that the possibility of analysing data offline shortly after a DAQ run was still vital. Reports on Recent Meetings 15. TDSG and Institutes Board at CERN Norman Gee The Institutes Board included a report from Cracow, the presentation of the summary of trigger activities (report included in minutes), a report from the referees meeting, guidelines for the proceedure for giving ATLAS related talks, and a discussion of changes to the Trigger/DAQ steering group in order to make it more effective. The Steering Group meeting had included a long discussion of the situation with the Compact Demonstrator program, and it was decided to endorse the view of the referees to stop the project after the development of TASIC2, ie not to proceed to the full PASIC production. There was also a discussion of the need for a Level 1 URD Level 2 had already gone through many iterations on their URD. Finally there was discussion of ATLAS introducing a common management scheme (using some form of Project Breakdown Schedule, or PBS). In both meetings the use of the new building 40 proved to be a hot topic. Eventually it was decided to leave the assignment of rooms to Nick Ellis. Building 40 has about 50 rooms, each of which is meant to be for 2, 3 or 4 people. The UK group had been assigned one office with several occupants, one being Nick. Many people from all groups were unhappy with the office arrangements. Suggestions of common working areas by many were unpopular with CERN. Norman also had an ATLAS schedule of activities up to the start of physics in 2005 that had been presented at the plenary. 6

7 16. Level 1 Trigger Meeting at CERN Tony Gillman There were only three items in the meeting. Firstly Tony had summarised the current demonstrator status. Ulrich then presented work on optical analogue data transmission, which was quite enlightening. The VCSELs he had tested turned out to be no better than the more conventional LED setup. The LED actually outperformed the VCSELs in dynamic range, and is also cheaper. There was also some question of the radiation hardness of VCSELs, which, all considered, makes Monnier's enthusiasm for VCSELs difficult to understand. Finally there was a round-table discussion of the integration of the groups activities now the Swedish program had been stopped. Ideas for the promotion of collaboration on various parts of the system were proposed, along with encouragement to keep lines of communication open. 17. Level 1/Level 2 Meeting at CERN Eric Eisenhandler Eric had presented the ROI information currently proposed to be formed by Level 1, which had provoked much discussion. Level 2 were in general shocked by the lack of information, so Eric then went on to describe what extra information could be made available, and of this extra data, which would be easy to provide, which hard. There would be a follow-up meeting to discuss this further in the near future. There was also a presentation by Nick on the Muon Interface. The Muon URD had already been completed. 18. Discussion with Calorimeter community Eric Eisenhandler This meeting was a follow-up to the front end electronics meeting. It was primarily attended by LAr people, but also some Tile Calorimeter were present. The first part was dedicated to BCID with Bill Cleland starting by presenting his analogue BCID. The main drive behind the CFD technique was that it saves a little in latency (perhaps two ticks). One novel feature was the simple transmission of signals below 5 GeV, without BCID. The effect of this needs some investigation. Bill Cleland had built some NIM hardware to try out analogue BCID. There was some disagreement about ADC noise levels at this stage. Dave then talked about digital BCID and the problem of resolution of close together signals was raised. Digital BCID does quite well with these, but Dave isnowinvestigated how the CFD technique works, and perhaps there is little difference. The general feeling was that digital BCID was fine, and a couple of ticks latency was unimportant. The meeting became rather less amiable after Jacques Colas presented his ideas for the trigger front end, where a major feature was scope access for the calorimeter group. The Level 1 group stated strongly that they should be responsible for building everything beyond the analogue cable from the detector. Just as we need to discuss the specification of the analogue summing to be done by the calorimeter group, they would discuss with us the specification for their access to the analogue signals in the counting room. Lists were compiled saying who was interested in which areas of the data chain. Since the meeting there has been little communication on this issue. However, it seems clear that the trigger tower sums will have to be done in close collaboration with Teiger, and so it might behelpful to arrange some talks in Paris to get this started. 7

8 Next Meeting There will probably be a small test-beam planning meeting before the next full meeting. The date of the next full meeting is: Friday 16 th August, 10:00 am, RAL 8

First Measurements with the ATLAS Level-1 Calorimeter Trigger PreProcessor System

First Measurements with the ATLAS Level-1 Calorimeter Trigger PreProcessor System First Measurements with the ATLAS Level-1 Calorimeter Trigger PreProcessor System The ATLAS Level-1 Calorimeter Trigger Collaboration R. Achenbach 1, P. Adragna 2, V. Andrei 1, B.M. Barnett 3, B. Bauss

More information

The ATLAS Tile Calorimeter, its performance with pp collisions and its upgrades for high luminosity LHC

The ATLAS Tile Calorimeter, its performance with pp collisions and its upgrades for high luminosity LHC The ATLAS Tile Calorimeter, its performance with pp collisions and its upgrades for high luminosity LHC Tomas Davidek (Charles University), on behalf of the ATLAS Collaboration Tile Calorimeter Sampling

More information

Level 1 Calorimeter Trigger:

Level 1 Calorimeter Trigger: ATL DA ES 0038 30 November 2006 EDMS document number 489129 Version Draft 0.6 Level 1 Calorimeter Trigger: DAQ and CMM cabling L1Calo Group 1 1 Introduction The purpose of this note is to complete the

More information

Hardware Verification after Installation. D0 Run IIB L1Cal Technical Readiness Review. Presented by Dan Edmunds August 2005

Hardware Verification after Installation. D0 Run IIB L1Cal Technical Readiness Review. Presented by Dan Edmunds August 2005 Hardware Verification after Installation D0 Run IIB L1Cal Technical Readiness Review Presented by Dan Edmunds 26-27 August 2005 The purpose of this talk is to describe to the committee how various aspects

More information

Update on DAQ for 12 GeV Hall C

Update on DAQ for 12 GeV Hall C Update on DAQ for 12 GeV Hall C Brad Sawatzky Hall C Winter User Group Meeting Jan 20, 2017 SHMS/HMS Trigger/Electronics H. Fenker 2 SHMS / HMS Triggers SCIN = 3/4 hodoscope planes CER = Cerenkov(s) STOF

More information

Trigger Cost & Schedule

Trigger Cost & Schedule Trigger Cost & Schedule Wesley Smith, U. Wisconsin CMS Trigger Project Manager DOE/NSF Review May 9, 2001 1 Baseline L4 Trigger Costs From April '00 Review -- 5.69 M 3.96 M 1.73 M 2 Calorimeter Trig. Costs

More information

BABAR IFR TDC Board (ITB): requirements and system description

BABAR IFR TDC Board (ITB): requirements and system description BABAR IFR TDC Board (ITB): requirements and system description Version 1.1 November 1997 G. Crosetti, S. Minutoli, E. Robutti I.N.F.N. Genova 1. Timing measurement with the IFR Accurate track reconstruction

More information

Update on DAQ for 12 GeV Hall C. Brad Sawatzky

Update on DAQ for 12 GeV Hall C. Brad Sawatzky Update on DAQ for 12 GeV Hall C Brad Sawatzky SHMS/HMS Trigger/Electronics H. Fenker 2 SHMS / HMS Triggers SCIN = 3/4 hodoscope planes CER = Cerenkov(s) STOF = S1 + S2 EL-Hi = SCIN + PSh_Hi EL-Lo = 2/3{SCIN,

More information

Local Trigger Electronics for the CMS Drift Tubes Muon Detector

Local Trigger Electronics for the CMS Drift Tubes Muon Detector Amsterdam, 1 October 2003 Local Trigger Electronics for the CMS Drift Tubes Muon Detector Presented by R.Travaglini INFN-Bologna Italy CMS Drift Tubes Muon Detector CMS Barrel: 5 wheels Wheel : Azimuthal

More information

Sharif University of Technology. SoC: Introduction

Sharif University of Technology. SoC: Introduction SoC Design Lecture 1: Introduction Shaahin Hessabi Department of Computer Engineering System-on-Chip System: a set of related parts that act as a whole to achieve a given goal. A system is a set of interacting

More information

Racks, Cabling and Latency

Racks, Cabling and Latency Racks, Cabling and Latency Murrough Landon 2 November 2000 Overview Rack Layout Cabling paths Latency estimates Outstanding issues "! #%$"! & % &(' Racks Layout Original Requirements Minimise the overall

More information

CMS Conference Report

CMS Conference Report Available on CMS information server CMS CR 1997/017 CMS Conference Report 22 October 1997 Updated in 30 March 1998 Trigger synchronisation circuits in CMS J. Varela * 1, L. Berger 2, R. Nóbrega 3, A. Pierce

More information

A Serializer ASIC at 5 Gbps for Detector Front-end Electronics Readout

A Serializer ASIC at 5 Gbps for Detector Front-end Electronics Readout A Serializer ASIC at 5 Gbps for Detector Front-end Electronics Readout Jingbo Ye, on behalf of the ATLAS Liquid Argon Calorimeter Group Department of Physics, Southern Methodist University, Dallas, Texas

More information

SuperB- DCH. Servizio Ele<ronico Laboratori FrascaA

SuperB- DCH. Servizio Ele<ronico Laboratori FrascaA 1 Outline 2 DCH FEE Constraints/Estimate & Main Blocks front- end main blocks Constraints & EsAmate Trigger rate (150 khz) Trigger/DAQ data format I/O BW Trigger Latency Minimum trigger spacing. Chamber

More information

The CALICE test beam programme

The CALICE test beam programme Journal of Physics: Conference Series The CALICE test beam programme To cite this article: F Salvatore 2009 J. Phys.: Conf. Ser. 160 012064 View the article online for updates and enhancements. Related

More information

WBS Trigger. Wesley Smith, U. Wisconsin CMS Trigger Project Manager. DOE/NSF Review April 11, 2000

WBS Trigger. Wesley Smith, U. Wisconsin CMS Trigger Project Manager. DOE/NSF Review April 11, 2000 WBS 3.1 - Trigger Wesley Smith, U. Wisconsin CMS Trigger Project Manager DOE/NSF Review April 11, 2000 US CMS DOE/NSF Review, April 11-13, 2000 1 Outline Overview of Calorimeter Trigger Calorimeter Trigger

More information

Commissioning and Initial Performance of the Belle II itop PID Subdetector

Commissioning and Initial Performance of the Belle II itop PID Subdetector Commissioning and Initial Performance of the Belle II itop PID Subdetector Gary Varner University of Hawaii TIPP 2017 Beijing Upgrading PID Performance - PID (π/κ) detectors - Inside current calorimeter

More information

ADF-2 Production Readiness Review

ADF-2 Production Readiness Review ADF-2 Production Readiness Review Presented by D. Edmunds 11-FEB-2005 The ADF-2 circuit board is part of the new Run IIB Level 1 Calorimeter Trigger. The purpose of this note is to provide the ADF-2 Production

More information

Installation of a DAQ System in Hall C

Installation of a DAQ System in Hall C Installation of a DAQ System in Hall C Cuore Collaboration Meeting Como, February 21 st - 23 rd 2007 S. Di Domizio A. Giachero M. Pallavicini S. Di Domizio Summary slide CUORE-like DAQ system installed

More information

Prospect and Plan for IRS3B Readout

Prospect and Plan for IRS3B Readout Prospect and Plan for IRS3B Readout 1. Progress on Key Performance Parameters 2. Understanding limitations during LEPS operation 3. Carrier02 Rev. C (with O-E-M improvements) 4. Pre-production tasks/schedule

More information

ATLAS Pixel Subsystem and Simulation

ATLAS Pixel Subsystem and Simulation ATLAS Pixel Subsystem and Simulation Charles Young On behalf of the SLAC ATLAS Team Annual DOE HEP Program Review (June 2007) 6/13/07 C. Young (Pixels and Simulation in ATLAS) 1 The Pixel Subsystem Basic

More information

Digital Signal Integrity and Stability in the ATLAS Level-1 Calorimeter Trigger

Digital Signal Integrity and Stability in the ATLAS Level-1 Calorimeter Trigger Digital Signal Integrity and Stability in the ATLAS Level-1 Calorimeter Trigger R. Achenbach b, P. Adragna d, M. Aharrouche c, V. Andrei b, B. Åsman f, B.M. Barnett e, B. Bauss c, M. Bendel c, C. Bohm

More information

CMS Tracker Synchronization

CMS Tracker Synchronization CMS Tracker Synchronization K. Gill CERN EP/CME B. Trocme, L. Mirabito Institut de Physique Nucleaire de Lyon Outline Timing issues in CMS Tracker Synchronization method Relative synchronization Synchronization

More information

Front End Electronics

Front End Electronics CLAS12 Ring Imaging Cherenkov (RICH) Detector Mid-term Review Front End Electronics INFN - Ferrara Matteo Turisini 2015 October 13 th Overview Readout requirements Hardware design Electronics boards Integration

More information

The Readout Architecture of the ATLAS Pixel System. 2 The ATLAS Pixel Detector System

The Readout Architecture of the ATLAS Pixel System. 2 The ATLAS Pixel Detector System The Readout Architecture of the ATLAS Pixel System Roberto Beccherle, on behalf of the ATLAS Pixel Collaboration Istituto Nazionale di Fisica Nucleare, Sez. di Genova Via Dodecaneso 33, I-646 Genova, ITALY

More information

Design, Realization and Test of a DAQ chain for ALICE ITS Experiment. S. Antinori, D. Falchieri, A. Gabrielli, E. Gandolfi

Design, Realization and Test of a DAQ chain for ALICE ITS Experiment. S. Antinori, D. Falchieri, A. Gabrielli, E. Gandolfi Design, Realization and Test of a DAQ chain for ALICE ITS Experiment S. Antinori, D. Falchieri, A. Gabrielli, E. Gandolfi Physics Department, Bologna University, Viale Berti Pichat 6/2 40127 Bologna, Italy

More information

WBS Calorimeter Trigger. Wesley Smith, U. Wisconsin CMS Trigger Project Manager. DOE/NSF Review April 12, 2000

WBS Calorimeter Trigger. Wesley Smith, U. Wisconsin CMS Trigger Project Manager. DOE/NSF Review April 12, 2000 WBS 3.1.2 - Calorimeter Trigger Wesley Smith, U. Wisconsin CMS Trigger Project Manager DOE/NSF Review April 12, 2000 1 Calorimeter Electronics Interface Calorimeter Trigger Overview 4K 1.2 Gbaud serial

More information

THE WaveDAQ SYSTEM FOR THE MEG II UPGRADE

THE WaveDAQ SYSTEM FOR THE MEG II UPGRADE Stefan Ritt, Paul Scherrer Institute, Switzerland Luca Galli, Fabio Morsani, Donato Nicolò, INFN Pisa, Italy THE WaveDAQ SYSTEM FOR THE MEG II UPGRADE DRS4 Chip 0.2-2 ns Inverter Domino ring chain IN Clock

More information

Paul Dauncey For the CALICE-UK electronics group. A. Baird, D. Bowerman, P. Dauncey, R. Halsall, M. Postranecky, M.Warren, O.

Paul Dauncey For the CALICE-UK electronics group. A. Baird, D. Bowerman, P. Dauncey, R. Halsall, M. Postranecky, M.Warren, O. ECAL Readout Paul Dauncey For the CALICE-UK electronics group A. Baird, D. Bowerman, P. Dauncey, R. Halsall, M. Postranecky, M.Warren, O. Zorba 8 December 2004 Paul Dauncey 1 CALICE Readout (ECAL) Card

More information

DAQ Systems in Hall A

DAQ Systems in Hall A CODA Users Workshop Data Acquisition at Jefferson Lab Newport News June 7, 2004 DAQ Systems in Hall A Overview of Hall A Standard Equipment: HRS, Beamline,... Parity Experiments Third Arms: BigBite, RCS

More information

LHC Beam Instrumentation Further Discussion

LHC Beam Instrumentation Further Discussion LHC Beam Instrumentation Further Discussion LHC Machine Advisory Committee 9 th December 2005 Rhodri Jones (CERN AB/BDI) Possible Discussion Topics Open Questions Tune measurement base band tune & 50Hz

More information

A new Scintillating Fibre Tracker for LHCb experiment

A new Scintillating Fibre Tracker for LHCb experiment A new Scintillating Fibre Tracker for LHCb experiment Alexander Malinin, NRC Kurchatov Institute on behalf of the LHCb-SciFi-Collaboration Instrumentation for Colliding Beam Physics BINP, Novosibirsk,

More information

Front End Electronics

Front End Electronics CLAS12 Ring Imaging Cherenkov (RICH) Detector Mid-term Review Front End Electronics INFN - Ferrara Matteo Turisini 2015 October 13 th Overview Readout requirements Hardware design Electronics boards Integration

More information

ECE 4220 Real Time Embedded Systems Final Project Spectrum Analyzer

ECE 4220 Real Time Embedded Systems Final Project Spectrum Analyzer ECE 4220 Real Time Embedded Systems Final Project Spectrum Analyzer by: Matt Mazzola 12222670 Abstract The design of a spectrum analyzer on an embedded device is presented. The device achieves minimum

More information

Test Beam Wrap-Up. Darin Acosta

Test Beam Wrap-Up. Darin Acosta Test Beam Wrap-Up Darin Acosta Agenda Darin/UF: General recap of runs taken, tests performed, Track-Finder issues Martin/UCLA: Summary of RAT and RPC tests, and experience with TMB2004 Stan(or Jason or

More information

SPS BPM system renovation. Roadmap & Milestones

SPS BPM system renovation. Roadmap & Milestones SPS BPM system renovation Roadmap & Milestones Synopsis Introduction and Overview: Andrea Infrastructures Fibres: Simao Cables: Joel Electronics Analogue Front-End: Manfred Digital Front-End: Manoel Back-End:

More information

Trigger Report. Wesley H. Smith CMS Trigger Project Manager Report to Steering Committee February 23, 2004

Trigger Report. Wesley H. Smith CMS Trigger Project Manager Report to Steering Committee February 23, 2004 Trigger Report Wesley H. Smith CMS Trigger Project Manager Report to Steering Committee February 23, 2004 Outline: Calorimeter Triggers Muon Triggers Global Triggers The pdf file of this talk is available

More information

Accelerator Controls Part2: CERN central timing system

Accelerator Controls Part2: CERN central timing system Accelerator Controls Part2: CERN central timing system CAS 2009@Divonne Hermann Schmickler Outline Part 2 Requested Functionality of the CERN timing system Implementation: Hardware Details Software Details:

More information

Atlas Pixel Replacement/Upgrade. Measurements on 3D sensors

Atlas Pixel Replacement/Upgrade. Measurements on 3D sensors Atlas Pixel Replacement/Upgrade and Measurements on 3D sensors Forskerskole 2007 by E. Bolle erlend.bolle@fys.uio.no Outline Sensors for Atlas pixel b-layer replacement/upgrade UiO activities CERN 3D test

More information

Development of beam-collision feedback systems for future lepton colliders. John Adams Institute for Accelerator Science, Oxford University

Development of beam-collision feedback systems for future lepton colliders. John Adams Institute for Accelerator Science, Oxford University Development of beam-collision feedback systems for future lepton colliders P.N. Burrows 1 John Adams Institute for Accelerator Science, Oxford University Denys Wilkinson Building, Keble Rd, Oxford, OX1

More information

Highly Accelerated Stress Screening of the Atlas Liquid Argon Calorimeter Front End Boards

Highly Accelerated Stress Screening of the Atlas Liquid Argon Calorimeter Front End Boards Highly Accelerated Stress Screening of the Atlas Liquid Argon Calorimeter Front End Boards K. Benslama, G. Brooijmans, C.-Y. Chi, D. Dannheim, I. Katsanos, J. Parsons, S. Simion Nevis Labs, Columbia University

More information

SciFi A Large Scintillating Fibre Tracker for LHCb

SciFi A Large Scintillating Fibre Tracker for LHCb SciFi A Large Scintillating Fibre Tracker for LHCb Roman Greim on behalf of the LHCb-SciFi-Collaboration 14th Topical Seminar on Innovative Particle Radiation Detectors, Siena 5th October 2016 I. Physikalisches

More information

TIME-COMPENSATED REMOTE PRODUCTION OVER IP

TIME-COMPENSATED REMOTE PRODUCTION OVER IP TIME-COMPENSATED REMOTE PRODUCTION OVER IP Ed Calverley Product Director, Suitcase TV, United Kingdom ABSTRACT Much has been said over the past few years about the benefits of moving to use more IP in

More information

KEK. Belle2Link. Belle2Link 1. S. Nishida. S. Nishida (KEK) Nov.. 26, Aerogel RICH Readout

KEK. Belle2Link. Belle2Link 1. S. Nishida. S. Nishida (KEK) Nov.. 26, Aerogel RICH Readout S. Nishida KEK Nov 26, 2010 1 Introduction (Front end electronics) ASIC (SA) Readout (Digital Part) HAPD (144ch) Preamp Shaper Comparator L1 buffer DAQ group Total ~ 500 HAPDs. ASIC: 36ch per chip (i.e.

More information

Glast beam test at CERN

Glast beam test at CERN Glast beam test at CERN Glast Collaboration Meeting 2005 R. Bellazzini 1 LAT beam test at CERN Main goals LAT-TD-02152, see Steve slides Required beam types and related measurements 1. tagged-photon beam

More information

SWITCH: Microcontroller Touch-switch Design & Test (Part 2)

SWITCH: Microcontroller Touch-switch Design & Test (Part 2) SWITCH: Microcontroller Touch-switch Design & Test (Part 2) 2 nd Year Electronics Lab IMPERIAL COLLEGE LONDON v2.09 Table of Contents Equipment... 2 Aims... 2 Objectives... 2 Recommended Timetable... 2

More information

First LHC Beams in ATLAS. Peter Krieger University of Toronto On behalf of the ATLAS Collaboration

First LHC Beams in ATLAS. Peter Krieger University of Toronto On behalf of the ATLAS Collaboration First LHC Beams in ATLAS Peter Krieger University of Toronto On behalf of the ATLAS Collaboration Cutaway View LHC/ATLAS (Graphic) P. Krieger, University of Toronto Aspen Winter Conference, Feb. 2009 2

More information

How to overcome/avoid High Frequency Effects on Debug Interfaces Trace Port Design Guidelines

How to overcome/avoid High Frequency Effects on Debug Interfaces Trace Port Design Guidelines How to overcome/avoid High Frequency Effects on Debug Interfaces Trace Port Design Guidelines An On-Chip Debugger/Analyzer (OCD) like isystem s ic5000 (Figure 1) acts as a link to the target hardware by

More information

A TARGET-based camera for CTA

A TARGET-based camera for CTA A TARGET-based camera for CTA TeV Array Readout with GSa/s sampling and Event Trigger (TARGET) chip: overview Custom-designed ASIC for CTA, developed in collaboration with Gary Varner (U Hawaii) Implementation:

More information

The Readout Architecture of the ATLAS Pixel System

The Readout Architecture of the ATLAS Pixel System The Readout Architecture of the ATLAS Pixel System Roberto Beccherle / INFN - Genova E-mail: Roberto.Beccherle@ge.infn.it Copy of This Talk: http://www.ge.infn.it/atlas/electronics/home.html R. Beccherle

More information

TORCH a large-area detector for high resolution time-of-flight

TORCH a large-area detector for high resolution time-of-flight TORCH a large-area detector for high resolution time-of-flight Roger Forty (CERN) on behalf of the TORCH collaboration 1. TORCH concept 2. Application in LHCb 3. R&D project 4. Test-beam studies TIPP 2017,

More information

DEDICATED TO EMBEDDED SOLUTIONS

DEDICATED TO EMBEDDED SOLUTIONS DEDICATED TO EMBEDDED SOLUTIONS DESIGN SAFE FPGA INTERNAL CLOCK DOMAIN CROSSINGS ESPEN TALLAKSEN DATA RESPONS SCOPE Clock domain crossings (CDC) is probably the worst source for serious FPGA-bugs that

More information

US CMS Endcap Muon. Regional CSC Trigger System WBS 3.1.1

US CMS Endcap Muon. Regional CSC Trigger System WBS 3.1.1 WBS Dictionary/Basis of Estimate Documentation US CMS Endcap Muon Regional CSC Trigger System WBS 3.1.1-1- 1. INTRODUCTION 1.1 The CMS Muon Trigger System The CMS trigger and data acquisition system is

More information

The ATLAS Level-1 Central Trigger

The ATLAS Level-1 Central Trigger he AAS evel-1 entral rigger RSpiwoks a, SAsk b, DBerge a, Daracinha a,c, NEllis a, PFarthouat a, PGallno a, SHaas a, PKlofver a, AKrasznahorkay a,d, AMessina a, Ohm a, Pauly a, MPerantoni e, HPessoa ima

More information

Designing Intelligence into Commutation Encoders

Designing Intelligence into Commutation Encoders I Designing Intelligence into Commutation Encoders By: Jeff Smoot, CUI Inc C U I NC Encoder users traditionally have been reluctant to change with good reason. Motor control on the factory floor or in

More information

arxiv: v1 [physics.ins-det] 1 Nov 2015

arxiv: v1 [physics.ins-det] 1 Nov 2015 DPF2015-288 November 3, 2015 The CMS Beam Halo Monitor Detector System arxiv:1511.00264v1 [physics.ins-det] 1 Nov 2015 Kelly Stifter On behalf of the CMS collaboration University of Minnesota, Minneapolis,

More information

The TRIGGER/CLOCK/SYNC Distribution for TJNAF 12 GeV Upgrade Experiments

The TRIGGER/CLOCK/SYNC Distribution for TJNAF 12 GeV Upgrade Experiments 1 1 1 1 1 1 1 1 0 1 0 The TRIGGER/CLOCK/SYNC Distribution for TJNAF 1 GeV Upgrade Experiments William GU, et al. DAQ group and Fast Electronics group Thomas Jefferson National Accelerator Facility (TJNAF),

More information

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala) 2 Work Package and Work Unit descriptions 2.8 WP8: RF Systems (R. Ruber, Uppsala) The RF systems work package (WP) addresses the design and development of the RF power generation, control and distribution

More information

Beam test of the QMB6 calibration board and HBU0 prototype

Beam test of the QMB6 calibration board and HBU0 prototype Beam test of the QMB6 calibration board and HBU0 prototype J. Cvach 1, J. Kvasnička 1,2, I. Polák 1, J. Zálešák 1 May 23, 2011 Abstract We report about the performance of the HBU0 board and the optical

More information

Previous Lecture Sequential Circuits. Slide Summary of contents covered in this lecture. (Refer Slide Time: 01:55)

Previous Lecture Sequential Circuits. Slide Summary of contents covered in this lecture. (Refer Slide Time: 01:55) Previous Lecture Sequential Circuits Digital VLSI System Design Prof. S. Srinivasan Department of Electrical Engineering Indian Institute of Technology, Madras Lecture No 7 Sequential Circuit Design Slide

More information

System: status and evolution. Javier Serrano

System: status and evolution. Javier Serrano CERN General Machine Timing System: status and evolution Javier Serrano CERN AB-CO-HT 15 February 2008 Outline Motivation Why timing systems at CERN? Types of CERN timing systems. The General Machine Timing

More information

Compact Muon Solenoid Detector (CMS) & The Token Bit Manager (TBM) Alex Armstrong & Wyatt Behn Mentor: Dr. Andrew Ivanov

Compact Muon Solenoid Detector (CMS) & The Token Bit Manager (TBM) Alex Armstrong & Wyatt Behn Mentor: Dr. Andrew Ivanov Compact Muon Solenoid Detector (CMS) & The Token Bit Manager (TBM) Alex Armstrong & Wyatt Behn Mentor: Dr. Andrew Ivanov Part 1: The TBM and CMS Understanding how the LHC and the CMS detector work as a

More information

The Alice Silicon Pixel Detector (SPD) Peter Chochula for the Alice Pixel Collaboration

The Alice Silicon Pixel Detector (SPD) Peter Chochula for the Alice Pixel Collaboration The Alice Silicon Pixel Detector (SPD) Peter Chochula for the Alice Pixel Collaboration The Alice Pixel Detector R 1 =3.9 cm R 2 =7.6 cm Main Physics Goal Heavy Flavour Physics D 0 K π+ 15 days Pb-Pb data

More information

PICOSECOND TIMING USING FAST ANALOG SAMPLING

PICOSECOND TIMING USING FAST ANALOG SAMPLING PICOSECOND TIMING USING FAST ANALOG SAMPLING H. Frisch, J-F Genat, F. Tang, EFI Chicago, Tuesday 6 th Nov 2007 INTRODUCTION In the context of picosecond timing, analog detector pulse sampling in the 10

More information

Online Monitoring of L1CT in Run IIa. bonus: experience from Run I

Online Monitoring of L1CT in Run IIa. bonus: experience from Run I Online Monitoring of L1CT in Run IIa bonus: experience from Run I Philippe Laurens 20-Feb-2003 L1 Cal Monitoring Monitoring can mean many things Anything related to observation of system s operation Different

More information

ALICE Muon Trigger upgrade

ALICE Muon Trigger upgrade ALICE Muon Trigger upgrade Context RPC Detector Status Front-End Electronics Upgrade Readout Electronics Upgrade Conclusions and Perspectives Dr Pascal Dupieux, LPC Clermont, QGPF 2013 1 Context The Muon

More information

TransitHound Cellphone Detector User Manual Version 1.3

TransitHound Cellphone Detector User Manual Version 1.3 TransitHound Cellphone Detector User Manual Version 1.3 RF3 RF2 Table of Contents Introduction...3 PC Requirements...3 Unit Description...3 Electrical Interfaces...4 Interface Cable...5 USB to Serial Interface

More information

Objectives. Combinational logics Sequential logics Finite state machine Arithmetic circuits Datapath

Objectives. Combinational logics Sequential logics Finite state machine Arithmetic circuits Datapath Objectives Combinational logics Sequential logics Finite state machine Arithmetic circuits Datapath In the previous chapters we have studied how to develop a specification from a given application, and

More information

AIDA Advanced European Infrastructures for Detectors at Accelerators. Milestone Report. Pixel gas read-out progress

AIDA Advanced European Infrastructures for Detectors at Accelerators. Milestone Report. Pixel gas read-out progress AIDA-MS41 AIDA Advanced European Infrastructures for Detectors at Accelerators Milestone Report Pixel gas read-out progress Colas, P. (CEA) et al 11 December 2013 The research leading to these results

More information

Optical Link Evaluation Board for the CSC Muon Trigger at CMS

Optical Link Evaluation Board for the CSC Muon Trigger at CMS Optical Link Evaluation Board for the CSC Muon Trigger at CMS 04/04/2001 User s Manual Rice University, Houston, TX 77005 USA Abstract The main goal of the design was to evaluate a data link based on Texas

More information

PRE-PROCESSOR MODULE

PRE-PROCESSOR MODULE Joint FDR/PRR of the PreProcessor Module: Report ATLAS Project Document. No. Institute Document No. Created : 18 December Page 1 of 21 ATC-RD-ER-0036 Modified: 08 March 2007 13 March 2007 Rev.No 1.1 1.2

More information

RF2TTC and QPLL behavior during interruption or switch of the RF-BC source

RF2TTC and QPLL behavior during interruption or switch of the RF-BC source RF2TTC and QPLL behavior during interruption or switch of the RF-BC source Study to adapt the BC source choice in RF2TTC during interruption of the RF timing signals Contents I. INTRODUCTION 2 II. QPLL

More information

Design of the Level-1 Global Calorimeter Trigger

Design of the Level-1 Global Calorimeter Trigger Design of the Level-1 Global Calorimeter Trigger For I reckon that the sufferings of this present time are not worthy to be compared with the glory which shall be revealed to us The epistle of Paul the

More information

Rome group activity since last meeting (4)

Rome group activity since last meeting (4) OLYMPUS Collaboration DESY 30/August/2010 Rome group activity since last meeting (4) DESY 30/August/2010 Olympus Collaboration meeting Salvatore Frullani / INFN-Rome Sanità Group 1 GEM electronics: Outline

More information

L12: Reconfigurable Logic Architectures

L12: Reconfigurable Logic Architectures L12: Reconfigurable Logic Architectures Acknowledgements: Materials in this lecture are courtesy of the following sources and are used with permission. Frank Honore Prof. Randy Katz (Unified Microelectronics

More information

High ResolutionCross Strip Anodes for Photon Counting detectors

High ResolutionCross Strip Anodes for Photon Counting detectors High ResolutionCross Strip Anodes for Photon Counting detectors Oswald H.W. Siegmund, Anton S. Tremsin, Robert Abiad, J. Hull and John V. Vallerga Space Sciences Laboratory University of California Berkeley,

More information

BABAR IFR TDC Board (ITB): system design

BABAR IFR TDC Board (ITB): system design BABAR IFR TDC Board (ITB): system design Version 1.1 12 december 1997 G. Crosetti, S. Minutoli, E. Robutti I.N.F.N. Genova 1. Introduction TDC readout of the IFR will be used during BABAR data taking to

More information

Performance of a double-metal n-on-n and a Czochralski silicon strip detector read out at LHC speeds

Performance of a double-metal n-on-n and a Czochralski silicon strip detector read out at LHC speeds Performance of a double-metal n-on-n and a Czochralski silicon strip detector read out at LHC speeds Juan Palacios, On behalf of the LHCb VELO group J.P. Palacios, Liverpool Outline LHCb and VELO performance

More information

CSE 352 Laboratory Assignment 3

CSE 352 Laboratory Assignment 3 CSE 352 Laboratory Assignment 3 Introduction to Registers The objective of this lab is to introduce you to edge-trigged D-type flip-flops as well as linear feedback shift registers. Chapter 3 of the Harris&Harris

More information

The Read-Out system of the ALICE pixel detector

The Read-Out system of the ALICE pixel detector The Read-Out system of the ALICE pixel detector Kluge, A. for the ALICE SPD collaboration CERN, CH-1211 Geneva 23, Switzerland Abstract The on-detector electronics of the ALICE silicon pixel detector (nearly

More information

An FPGA based Topological Processor Prototype for the ATLAS Level-1 Trigger Upgrade

An FPGA based Topological Processor Prototype for the ATLAS Level-1 Trigger Upgrade Preprint typeset in JINST style - HYPER VERSION An FPGA based Topological Processor Prototype for the ATLAS Level-1 Trigger Upgrade Bruno Bauss, Volker Büscher, Reinhold Degele, Weina Ji, Sebastian Moritz,

More information

FPGA Design. Part I - Hardware Components. Thomas Lenzi

FPGA Design. Part I - Hardware Components. Thomas Lenzi FPGA Design Part I - Hardware Components Thomas Lenzi Approach We believe that having knowledge of the hardware components that compose an FPGA allow for better firmware design. Being able to visualise

More information

Conceps and trends for Front-end chips in Astroparticle physics

Conceps and trends for Front-end chips in Astroparticle physics Conceps and trends for Front-end chips in Astroparticle physics Eric Delagnes Fabrice Feinstein CEA/DAPNIA Saclay LPTA/IN2P3 Montpellier General interest performances Fast pulses : bandwidth > ~ 300 MHz

More information

L11/12: Reconfigurable Logic Architectures

L11/12: Reconfigurable Logic Architectures L11/12: Reconfigurable Logic Architectures Acknowledgements: Materials in this lecture are courtesy of the following people and used with permission. - Randy H. Katz (University of California, Berkeley,

More information

The Silicon Pixel Detector (SPD) for the ALICE Experiment

The Silicon Pixel Detector (SPD) for the ALICE Experiment The Silicon Pixel Detector (SPD) for the ALICE Experiment V. Manzari/INFN Bari, Italy for the SPD Project in the ALICE Experiment INFN and Università Bari, Comenius University Bratislava, INFN and Università

More information

An Overview of Beam Diagnostic and Control Systems for AREAL Linac

An Overview of Beam Diagnostic and Control Systems for AREAL Linac An Overview of Beam Diagnostic and Control Systems for AREAL Linac Presenter G. Amatuni Ultrafast Beams and Applications 04-07 July 2017, CANDLE, Armenia Contents: 1. Current status of existing diagnostic

More information

A prototype of fine granularity lead-scintillating fiber calorimeter with imaging read-out

A prototype of fine granularity lead-scintillating fiber calorimeter with imaging read-out A prototype of fine granularity lead-scintillating fiber calorimeter with imaging read-out P.Branchini, F.Ceradini, B.Di Micco, A. Passeri INFN Roma Tre and Dipartimento di Fisica Università Roma Tre and

More information

Electronics Status and Upgrade Opportunities for Flash ADC and 12GeV Trigger Hardware

Electronics Status and Upgrade Opportunities for Flash ADC and 12GeV Trigger Hardware Electronics Status and Upgrade Opportunities for Flash ADC and 12GeV Trigger Hardware R. Chris Cuevas Group Leader Fast Electronics NPS Collaboration Meeting Jefferson Lab 14-November-2013 Page 1 OUTLINE

More information

EECS150 - Digital Design Lecture 2 - CMOS

EECS150 - Digital Design Lecture 2 - CMOS EECS150 - Digital Design Lecture 2 - CMOS January 23, 2003 John Wawrzynek Spring 2003 EECS150 - Lec02-CMOS Page 1 Outline Overview of Physical Implementations CMOS devices Announcements/Break CMOS transistor

More information

Note on the preliminary organisation for the design, fabrication and test of a prototype double-sided ladder equipped with MAPS

Note on the preliminary organisation for the design, fabrication and test of a prototype double-sided ladder equipped with MAPS Note on the preliminary organisation for the design, fabrication and test of a prototype double-sided ladder equipped with MAPS J.Baudot a, J.Goldstein b, A.Nomerotski c, M.Winter a a IPHC - Université

More information

HAPD and Electronics Updates

HAPD and Electronics Updates S. Nishida KEK 3rd Open Meeting for Belle II Collaboration 1 Contents Frontend Electronics Neutron Irradiation News from Hamamtsu 2 144ch HAPD HAPD (Hybrid Avalanche Photo Detector) photon bi alkali photocathode

More information

FPGA Development for Radar, Radio-Astronomy and Communications

FPGA Development for Radar, Radio-Astronomy and Communications John-Philip Taylor Room 7.03, Department of Electrical Engineering, Menzies Building, University of Cape Town Cape Town, South Africa 7701 Tel: +27 82 354 6741 email: tyljoh010@myuct.ac.za Internet: http://www.uct.ac.za

More information

A FOUR GAIN READOUT INTEGRATED CIRCUIT : FRIC 96_1

A FOUR GAIN READOUT INTEGRATED CIRCUIT : FRIC 96_1 A FOUR GAIN READOUT INTEGRATED CIRCUIT : FRIC 96_1 J. M. Bussat 1, G. Bohner 1, O. Rossetto 2, D. Dzahini 2, J. Lecoq 1, J. Pouxe 2, J. Colas 1, (1) L. A. P. P. Annecy-le-vieux, France (2) I. S. N. Grenoble,

More information

Zebra2 (PandA) Functionality and Development. Isa Uzun and Tom Cobb

Zebra2 (PandA) Functionality and Development. Isa Uzun and Tom Cobb Zebra2 (PandA) Functionality and Development Isa Uzun and Tom Cobb Control Systems Group 27 April 2016 Outline Part - I ZEBRA and Motivation Hardware Architecture Functional Capabilities Part - II Software

More information

SuperFRS GEM-TPC Development Status Report

SuperFRS GEM-TPC Development Status Report SuperFRS GEM-TPC Development Status Report COLLABORATORS F. García, R. Turpeinen, J. Heino, A. Karadzhinova, E. Tuominen, R. Lauhakangas Helsinki Institute of Physics University of Helsinki - Finland R.

More information

Solutions to Embedded System Design Challenges Part II

Solutions to Embedded System Design Challenges Part II Solutions to Embedded System Design Challenges Part II Time-Saving Tips to Improve Productivity In Embedded System Design, Validation and Debug Hi, my name is Mike Juliana. Welcome to today s elearning.

More information

PHOTOTUBE SCANNING SETUP AT THE UNIVERSITY OF MARYLAND. Doug Roberts U of Maryland, College Park

PHOTOTUBE SCANNING SETUP AT THE UNIVERSITY OF MARYLAND. Doug Roberts U of Maryland, College Park PHOTOTUBE SCANNING SETUP AT THE UNIVERSITY OF MARYLAND Doug Roberts U of Maryland, College Park Overview We have developed a system for measuring and scanning phototubes for the FDIRC Based primarily on

More information

Global Trigger Trigger meeting 27.Sept 00 A.Taurok

Global Trigger Trigger meeting 27.Sept 00 A.Taurok Global Trigger Trigger meeting 27.Sept 00 A.Taurok Global Trigger Crate GT crate VME 9U Backplane 4 MUONS parallel CLOCK, BC_Reset... READOUT _links PSB 12 PSB 12 24 4 6 GT MU 6 GT MU PSB 12 PSB 12 PSB

More information

Electronics procurements

Electronics procurements Electronics procurements 24 October 2014 Geoff Hall Procurements from CERN There are a wide range of electronics items procured by CERN but we are familiar with only some of them Probably two main categories:

More information

S.Cenk Yıldız on behalf of ATLAS Muon Collaboration. Topical Workshop on Electronics for Particle Physics, 28 September - 2 October 2015

S.Cenk Yıldız on behalf of ATLAS Muon Collaboration. Topical Workshop on Electronics for Particle Physics, 28 September - 2 October 2015 THE ATLAS CATHODE STRIP CHAMBERS A NEW ATLAS MUON CSC READOUT SYSTEM WITH SYSTEM ON CHIP TECHNOLOGY ON ATCA PLATFORM S.Cenk Yıldız on behalf of ATLAS Muon Collaboration University of California, Irvine

More information