SLAC ILC Accelerator R&D Program

Size: px
Start display at page:

Download "SLAC ILC Accelerator R&D Program"

Transcription

1 SLAC ILC Accelerator R&D Program SLUO Meeting September 26 th, 2005 Tor Raubenheimer

2 SLAC 2005 ILC Program NLC group was redirected towards ILC Developed a program aimed at the topics identified in the 2003 Technical Review Committee report and at the 1 st ILC Workshop Description at: The 2003 TRC identified 1 R1 and 15 R2 R&D items DESY, Fermilab, and KEK are focused on the outstanding R1 and the R2 on the linac sub-unit test SLAC is focused on the other 14 of the 15 R2 items and is working with US labs, KEK, UK groups, and DESY SLAC used technical expertise to study paths for cost reduction High power rf (klystrons, couplers, circulators, and rf distribution) and solid state modulators Major participation at ILC Workshops (KEK and Snowmass)

3 Snowmass LC Meeting

4 SLAC 2006 ILC Program Program for FY06 has two main elements Development of the ILC RDR (Reference Design Report) Overall design: Beam parameters, Optics, Emittance preservation, Stability/alignment, Instrumentation, Availability, MPS, and Operational issues Electron & Positron sources and Damping rings Linac design and wakefields/cavity optimization Beam Delivery System and Interaction Region Conventional construction implications and site development Continuing R&D on linac rf technology for better cost & performance Modulators, rf distribution, and couplers Not (much) SC Cavity fabrication Worked with Barry Barish and Gerry Dugan to develop plan

5 Experimental Basis for the ILC Design SLC, FFTB, ASSET, E-158 Bunch Compression SLC and FEL s SLC and (ATF2 in the future) ε Preservation TESLA Test Facility (SMTF & STF in the future) Linac rf system BDS & IR ATF, 3 rd Gen Light Sources, SLC SLC, E-158 e+ / e- Sources Damping Rings

6 Accelerator Design (Reference Design Report) SLAC has a very strong accelerator design group Have thought about most aspects of the LC design and ops We have groups focused on most subsystems with the exception of the SC cavity fabrication Sources Damping rings Bunch compressor, prelinac collimation, and spin rotator Linac rf system and linac beamline Beam delivery system Collaboration building is another large part of our efforts Work on FNAL, ATF and KEK, DESY Coordination of BDS, MDI, instrumentation projects, LET, e+

7 L-Band RF System R&D SLAC has strong expertise in rf power generation and lots of experience from the X-band rf program to apply to ILC Goal: reduce cost of the rf system (which is roughly 15% of TPC in USLCTOS cost estimate) and improve performance (better reliability, higher efficiency, ) Working on solid state modulators, L-band klystrons, and other rf components Collaborating with Fermilab on three projects for the SMTF: Modulator switches Bayonet box for cryo-system Electron-beam welding of SC cavities Would like to do more couplers for example

8 Major Test Facilities End Station B Support Advanced Acceleration experiments (including X-band work) Create new L-band rf Test Facility Develop klystron and modulators for ILC Test normal conducting structures for e+/e- sources Construct coupler test facility Facilities also available in Klystron Test Lab End Station A Study Interaction Region issues and instrumentation Mockup of full IR ATF/ATF-2 (Located at KEK but with big SLAC participation) Test final focus system using very low emittance beam Work on the linac test facilities around the world: DESY, FNAL, and KEK

9 Electron and Positron Sources Electron source Continuing photocathode development Creating space to begin laser and gun development Need to start design simulations Positron source (program with LLNL) Studying target design for undulator, conventional, and Compton sources Radiation damage Thermal shock / beam damage Engineering issues (high rotation speed, remote handling) Capture and optics studies Normal conducting capture structure design and fabrication Complete E-166 polarized positron production (summer 2005)

10 Accelerator Structures (e+ and e- Sources) Need normal conducting structures for capture regions in the electron and positron sources Problems with rf heating and possibly beam loss Building ½ length standing-wave structure to be tested in End Station B facility with 5MW of rf power Fabrication started installation in spring

11 E-166: Polarized Positrons (June 2005 Run)

12 Damping Ring Aperture (Beam Dynamics Studies) New optics proposed based on PEP-II non-interleaved sextupole correction Pi-cell and FODO cell designs Dynamic aperture in Dogbone Damping Ring designs TME (DESY TDR) Pi-cell (low α Pep-II) FODO (high α Pep-II) Injected positron beam: ε x = ε y = 1x10-6 m-rad, tracked using LEGO with single-mode wigglers and multipole errors in the other magnets.

13 ATF Damping KEK (Low Emittance Source) Prototype electron damping ring with strong SLAC participation SLAC visits totaling 1 FTE last year Hardware and software projects BPM and other instrumentation Kicker magnets (fast kicker R&D and extraction kicker replacement) Beam-based alignment and ORM procedures (later used on PEP-II) Instability studies and Emittance tuning (lowest emittance source in world)

14 New ATF Extraction Kicker Refurbished SLC kickers for ATF Shipped July 05 for installation Oct ns long pulse to prep ATF for ILC-like beam extraction A

15 Fast Damping Ring Kickers (Damping Ring Design) High speed ring damping kicker developed by LLNL/SLAC 3kV with 5ns rise time and 10ns flat top Tested at the ATF damping ring

16 Secondary Electron Yield (Damping Ring Instabilities) Test chambers being constructed for installation in PEP-II in 2005/2006 Test different samples in real environment Test grooved chambers as a potential solution

17 Superconducting Linac Quad (Linac Beam Dynamics) Understand limitations of beam-based alignment techniques by measuring SC quadrupole Need to achieve ~25 um alignment Requires center motion of less than few um as excitation is varied SC Quad Constructed in Spain for DESY SLAC is building cryostat RF BPM Working with KEK and LCLS on rf bpm design Test integrated quad/bpm package in 2006

18 High Resolution BPMs Rf BPMs tested at ATF ~20 nm resolution measured Building electronics for ATF2 bpms HOM detectors tested at TTF 8 um resolution measured against TTF BPMs 16 um resolution comparing against other modes

19 TTF Cavity HOM Project (Linac Diagnostics) TTF HOM signals used for beam feedback stabilize FEL beam ACC4 Dipole signal versus time Building electronics for 40 more systems for TTF-2 Offset Use of HOM BPM signals for beam position offset nulling feedback Linda Hendrickson / Joe Frisch Pulse number

20 Beam Delivery System (System Design) Dual IR baseline design independent incoming & outgoing beamlines SC Quads from BNL The baseline for two IRs has greater flexibility: Independent incoming and outgoing beamlines, higher luminosity reach, flexibility in operation, upgradeability to γγ in 20mrad IR Better background & detector hermeticity (with less luminosity reach, poorer diagnostics & less operational flexibility) in 2mrad IR Two detectors in truly independent collider halls

21 Beam Delivery System (System Design) Single IR design concept In a single IR, do not have to separate incoming beamlines Crossing angle can be minimized to reduce backgrounds etc but still keep advantages of independent incoming and outgoing beamlines Limitation is due to incoming/outgoing magnet separation BNL 380mm QD0 Prototype Compact SC Final Quad compensating coil fringefield-free extraction aperture

22 ATF-2 at KEK ATF-2 would be the BDS test facility Follow-on to FFTB New FFS optics Operational issues Train next generation ILC like optics at ATF-2 New final focus

23 End Station A Test Facility For Prototypes of Beam Delivery and IR Components Collimator design, wakefields (T-480) Begin in November BPM energy spectrometer (T-474) Synch Stripe energy spectrometer (T-475) IP BPMs, kickers EMI (electro-magnetic interference) IR Mockup PAC05 paper/poster: SLAC-PUB-11180, e-print Archive: physics/ CCLRC LLNL QMUL U. of Bristol UMass Amherst CERN Lancaster U. SLAC UC Berkeley U. of Oregon DESY Manchester U. TU Darmstadt U. of Cambridge KEK Notre Dame U. of Birmingham UCL

24 End Station A: T-474 rf cavity BPMs at ASSET for E158 Initially, will use SLAC Linac BPMs. New electronics based on nanobpm work at KEK, being developed by UC Berkeley diameter rf cavity BPMs moved from SLAC Linac to End Station A rf cavity BPM New BPMs, optimized for energy spectrometer, to be designed at University College London and in collaboration with BPM experts at SLAC and KEK

25 Civil Design and Siting

26 Availability and Operations The ILC will be an order of magnitude more complex than any accelerator ever built If it is built like present HEP accelerators, it will be down an order of magnitude more (essentially always down) For reasonable uptime, component availability must be much better than ever before requires serious R&D Device Required MTBF Improvement Factor MTBF from Present Experience (khours) magnets - water cooled 20 1,000 power supply controllers flow switches water instrumention near pump power supplies kicker pulser coupler interlock sensors 5 1,000 collimators and beam stoppers all electronics modules AC breakers < 500 kw vacuum valve controllers regional MPS system 5 5 power supply - corrector vacuum valves 3 1,000 water pumps modulator 50 klystron - linac 40 coupler interlock electronics 1,000

27 L-Band RF System

28 Marx Generator Modulator High efficiency Marx Generator modulator being designed Modular system for lower cost and greater availability High voltage operation to simply design and linac tunnel Marx generator test area

29 Marx Generator Modulator

30 Klystrons (RF Power Generation) DESY 10 MW Klystron Program Three Thales tubes built, five more ordered two have meet full specs (but only run a few hundred hours) One CPI tube built achieved 10 MW at short pulse length, limited by CPI modulator may come to SLAC after testing at DESY One Toshiba tube built and under test 10 MW, 1 ms achieved SLAC Klystron Program Developing a 10 MW L-band Sheet-Beam Klystron (currently no funding) If multi-beam program falters, consider lower perveance, single beam, 5 MW tube, possibly with PPM focusing Buy commercial 5 MW tubes as needed for L-band program Possibly collaborate with DESY and CPI on 10 MW tube

31 L-band RF Station (End Station B) Begged, borrowed, or stole most components for a 5MW L-band rf station 1 st power in 3 months New 5MW klystron arriving next year we have one to start with

32 End Station B: ILC Program L-Band RF Test Facility Build two L-band test stations next to NLCTA in ESB Test modulators and klystrons Provide rf power for NC accelerator structures and couplers

33 Summary Broad program SLAC group is recognized as excellent throughout the world Strong design effort with beam dynamics studies, integrated R&D and engineering studies Experimental program is picking up speed NLCTA is operating; L-band rf station is being constructed in ESB End Station A program should be starting up soon Working at ATF and working on ATF-2 at KEK Working on TTF-2 at DESY Lots of projects coming to fruition in 2006 Lots to do! New people coming on board Contact us if interested in ILC!

SLAC ILC program, International BDS Design, ATF2 facility

SLAC ILC program, International BDS Design, ATF2 facility 1 May 3, 2005 SLAC ILC program, International BDS Design, ATF2 facility Andrei Seryi May 3, 2005 Seminar at CERN 2 May 3, 2005 Contents SLAC ILC program» following the outline given by Tor Raubenheimer

More information

L-Band RF R&D. SLAC DOE Review June 15 th, Chris Adolphsen SLAC

L-Band RF R&D. SLAC DOE Review June 15 th, Chris Adolphsen SLAC L-Band RF R&D SLAC DOE Review June 15 th, 2005 Chris Adolphsen SLAC International Linear Collider (ILC) RF Unit (TESLA TDR Layout) Gradient = 23.4 MV/m Bunch Spacing = 337 ns Fill Time = 420 µs Train Length

More information

Focus of efforts. ILC 2010, Mar/27/10 A. Seryi, BDS: 2

Focus of efforts. ILC 2010, Mar/27/10 A. Seryi, BDS: 2 Beam Delivery System Updates Andrei Seryi for BDS design and ATF2 commissioning teams LCWS 2010 / ILC 2010 March 28, 2010 Plan of the program at ILC2010 Focus of efforts Work on parameter set for a possible

More information

Nick Walker DESY MAC

Nick Walker DESY MAC Nick Walker DESY MAC 4.5.2006 XFEL X-Ray Free-Electron Laser DESY ILC Project Group Accelerator Experimentation Behnke, Elsen, Walker (chair) WP 15, 16 WP 4-7 Accelerator Physics and Design WP 6 High Gradient

More information

Availability and Reliability Issues for the ILC

Availability and Reliability Issues for the ILC Availability and Reliability Issues for the ILC SLAC Presented at PAC07 26 June 07 Contents Introduction and purpose of studies The availability simulation What was modeled (important assumptions) Some

More information

PEP II Design Outline

PEP II Design Outline PEP II Design Outline Balša Terzić Jefferson Lab Collider Review Retreat, February 24, 2010 Outline General Information Parameter list (and evolution), initial design, upgrades Collider Ring Layout, insertions,

More information

Accelerator Instrumentation RD. Monday, July 14, 2003 Marc Ross

Accelerator Instrumentation RD. Monday, July 14, 2003 Marc Ross Monday, Marc Ross Linear Collider RD Most RD funds address the most serious cost driver energy The most serious impact of the late technology choice is the failure to adequately address luminosity RD issues

More information

SUMMARY OF THE ILC R&D AND DESIGN

SUMMARY OF THE ILC R&D AND DESIGN SUMMARY OF THE ILC R&D AND DESIGN B. C. Barish, California Institute of Technology, USA Abstract The International Linear Collider (ILC) is a linear electron-positron collider based on 1.3 GHz superconducting

More information

WG2 Group Summary. Chris Adolphsen Terry Garvey Hitoshi Hayano

WG2 Group Summary. Chris Adolphsen Terry Garvey Hitoshi Hayano WG2 Group Summary Chris Adolphsen Terry Garvey Hitoshi Hayano Linac Options Fest On Thursday afternoon, various experts summarized the linac baseline options. Although hard choices have yet to be made,

More information

STATUS OF THE INTERNATIONAL LINEAR COLLIDER

STATUS OF THE INTERNATIONAL LINEAR COLLIDER STATUS OF THE INTERNATIONAL LINEAR COLLIDER K. Yokoya, KEK, Tsukuba, Japan Abstract The International Linear Collider (ILC) is the nextgeneration electron-positron collider. Since the publication of the

More information

5 Project Costs and Schedule

5 Project Costs and Schedule 93 5 Project Costs and Schedule 5.1 Overview The cost evaluation for the integrated version of the XFEL with 30 experiments and 35 GeV beam energy as described in the TDR-2001 yielded 673 million EUR for

More information

A Facility for Accelerator Physics and Test Beam Experiments

A Facility for Accelerator Physics and Test Beam Experiments A Facility for Accelerator Physics and Test Beam Experiments U.S. Department of Energy Review Roger Erickson for the FACET Design Team February 20, 2008 SLAC Overview with FACET FACET consists of four

More information

Present Status and Future Upgrade of KEKB Injector Linac

Present Status and Future Upgrade of KEKB Injector Linac Present Status and Future Upgrade of KEKB Injector Linac Kazuro Furukawa, for e /e + Linac Group Present Status Upgrade in the Near Future R&D towards SuperKEKB 1 Machine Features Present Status and Future

More information

PEP II STATUS AND PLANS *

PEP II STATUS AND PLANS * PEP II STATUS AND PLANS * John T. Seeman + Stanford Linear Accelerator Center, Stanford University, Stanford, CA 94309 USA The PEP II B-Factory 1 project is an e + e - colliding beam storage ring complex

More information

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline 3 cerl 3-1 cerl Overview As described before, the aim of the cerl in the R&D program includes the development of critical components for the ERL, as well as the construction of a test accelerator. The

More information

SLAC X-band Technology R&D. Tor Raubenheimer DOE Briefing June 11 th, 2010

SLAC X-band Technology R&D. Tor Raubenheimer DOE Briefing June 11 th, 2010 SLAC X-band Technology R&D Tor Raubenheimer DOE Briefing June 11 th, 2010 Introduction Overall ARD strategy ILC Program X-band program Compact XFEL and other applications Status and development needs Proposed

More information

Status and Plans for PEP-II

Status and Plans for PEP-II Status and Plans for PEP-II John Seeman SLAC Particle and Particle-Astrophysics DOE HEPAP P5 Review April 21, 2006 Topics Luminosity records for PEP-II in October 2005 Fall shut-down upgrades Run 5b turn

More information

PEP II Status and Plans

PEP II Status and Plans SLAC-PUB-6854 September 1998 PEP II Status and Plans By John T. Seeman Invited talk presented at the 16th IEEE Particle Accelerator Conference (PAC 95) and International Conference on High Energy Accelerators,

More information

Overview of the X-band R&D Program

Overview of the X-band R&D Program Overview of the X-band R&D Program SLAC-PUB-9442 August 2002 Abstract T.O. Raubenheimer Stanford Linear Accelerator Center, Stanford University, Stanford, California 94309 USA An electron/positron linear

More information

ILC Damping Ring Lattice Status Report. Louis Emery and Aimin Xiao Argonne National Laboratory Presented at KEK workshop Dec 18th, 2007

ILC Damping Ring Lattice Status Report. Louis Emery and Aimin Xiao Argonne National Laboratory Presented at KEK workshop Dec 18th, 2007 Status Report Louis Emery and Aimin Xiao Argonne National Laboratory Presented at KEK workshop Dec 18th, 2007 Outline New 8-fold symmetric lattice on ILC Cornell wiki pages, as of 12/18/2007 Separated

More information

INFN School on Electron Accelerators. RF Power Sources and Distribution

INFN School on Electron Accelerators. RF Power Sources and Distribution INFN School on Electron Accelerators 12-14 September 2007, INFN Sezione di Pisa Lecture 7b RF Power Sources and Distribution Carlo Pagani University of Milano INFN Milano-LASA & GDE The ILC Double Tunnel

More information

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

Diamond RF Status (RF Activities at Daresbury) Mike Dykes Diamond RF Status (RF Activities at Daresbury) Mike Dykes ASTeC What is it? What does it do? Diamond Status Linac Booster RF Storage Ring RF Summary Content ASTeC ASTeC was formed in 2001 as a centre of

More information

What can be learned from HERA Experience for ILC Availability

What can be learned from HERA Experience for ILC Availability What can be learned from HERA Experience for ILC Availability August 17, 2005 F. Willeke, DESY HERA Performance Critical Design Decisions What could be avoided if HERA would have to be built again? HERA

More information

NLC - The Next Linear Collider Project NLC R&D. D. L. Burke. DOE Annual Program Review SLAC April 9-11, 2003

NLC - The Next Linear Collider Project NLC R&D. D. L. Burke. DOE Annual Program Review SLAC April 9-11, 2003 DOE Annual Program Review SLAC April 9-11, 2003 NLC Activities for the Past Year Accelerator Design centered around ILC-TRC studies. Technology R&D focused on the RF R&D. Modulator, klystron, SLED-II,

More information

SPEAR 3: Operations Update and Impact of Top-Off Injection

SPEAR 3: Operations Update and Impact of Top-Off Injection SPEAR 3: Operations Update and Impact of Top-Off Injection R. Hettel for the SSRL ASD 2005 SSRL Users Meeting October 18, 2005 SPEAR 3 Operations Update and Development Plans Highlights of 2005 SPEAR 3

More information

The Elettra Storage Ring and Top-Up Operation

The Elettra Storage Ring and Top-Up Operation The Elettra Storage Ring and Top-Up Operation Emanuel Karantzoulis Past and Present Configurations 1994-2007 From 2008 5000 hours /year to the users 2010: Operations transition year Decay mode, 2 GeV (340mA)

More information

THE NEXT LINEAR COLLIDER TEST ACCELERATOR: STATUS AND RESULTS * Abstract

THE NEXT LINEAR COLLIDER TEST ACCELERATOR: STATUS AND RESULTS * Abstract SLAC PUB 7246 June 996 THE NEXT LINEAR COLLIDER TEST ACCELERATOR: STATUS AND RESULTS * Ronald D. Ruth, SLAC, Stanford, CA, USA Abstract At SLAC, we are pursuing the design of a Next Linear Collider (NLC)

More information

Working Group 2 Introductory presentation. Convenors C. Adolphsen, T. Garvey, H. Hayano

Working Group 2 Introductory presentation. Convenors C. Adolphsen, T. Garvey, H. Hayano Working Group 2 Introductory presentation. Convenors C. Adolphsen, T. Garvey, H. Hayano Topics covered by WG2 Modulators / klystrons RF wave-guide distribution Low Level RF Beam interfaces (quadrupoles,

More information

Andrei Seryi, Toshiaki Tauchi. December 15-18, 2008

Andrei Seryi, Toshiaki Tauchi. December 15-18, 2008 ATF2 milestones for discussion Andrei Seryi, Toshiaki Tauchi December 15-18, 2008 7th ATF2 Project Meeting What are natural milestones for ATF2? ATF2 design: Nominal IP β y* =0.1 mm & L * =1 m this give

More information

Towards an X-Band Power Source at CERN and a European Structure Test Facility

Towards an X-Band Power Source at CERN and a European Structure Test Facility Towards an X-Band Power Source at CERN and a European Structure Test Facility Erk Jensen and Gerry McMomagle CERN The X-Band Accelerating Structure Design and Test-Program Workshop Day 2: Structure Testing

More information

Development of beam-collision feedback systems for future lepton colliders. John Adams Institute for Accelerator Science, Oxford University

Development of beam-collision feedback systems for future lepton colliders. John Adams Institute for Accelerator Science, Oxford University Development of beam-collision feedback systems for future lepton colliders P.N. Burrows 1 John Adams Institute for Accelerator Science, Oxford University Denys Wilkinson Building, Keble Rd, Oxford, OX1

More information

RF considerations for SwissFEL

RF considerations for SwissFEL RF considerations for H. Fitze in behalf of the PSI RF group Workshop on Compact X-Ray Free Electron Lasers 19.-21. July 2010, Shanghai Agenda Introduction RF-Gun Development C-band development Summary

More information

November 5,1999. The NLC Injector UCRL-JC

November 5,1999. The NLC Injector UCRL-JC Preprint UCRL-JC-13-6450 The NLC Injector System V. Bharadwaj, J.E. Clendenin, P. Emma, J. Frisch, R.K. Jobe, T. Kotseroglou, P. Krejcik, A. V. Kulikov, Z. Li, T. Maruyama, K.K. Millage, B. McKee, G. Mulhollan,

More information

Status of Elettra, top-up and other upgrades

Status of Elettra, top-up and other upgrades Status of Elettra, top-up and other upgrades Emanuel Karantzoulis ELETTRA / Trieste, Italy / 2010 November 25-26 Past and Present Configurations 1994-2007 From 2008 No full energy injection Full energy

More information

P. Emma, et al. LCLS Operations Lectures

P. Emma, et al. LCLS Operations Lectures P. Emma, et al. LCLS Operations Lectures LCLS 1 LCLS Accelerator Schematic 6 MeV 135 MeV 250 MeV σ z 0.83 mm σ z 0.83 mm σ z 0.19 mm σ δ 0.05 % σ δ 0.10 % σ δ 1.6 % Linac-0 L =6 m rf gun L0-a,b Linac-1

More information

Next Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack

Next Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack The Four 50 MW XL4 X-band klystrons installed on the 8-Pack The Demonstrate an NLC power source Two Phases: 8-Pack Phase-1 (current): Multi-moded SLED II power compression Produce NLC baseline power: 475

More information

Detailed Design Report

Detailed Design Report Detailed Design Report Chapter 4 MAX IV Injector 4.6. Acceleration MAX IV Facility CHAPTER 4.6. ACCELERATION 1(10) 4.6. Acceleration 4.6. Acceleration...2 4.6.1. RF Units... 2 4.6.2. Accelerator Units...

More information

PEP-II STATUS REPORT *

PEP-II STATUS REPORT * PEP-II STATUS REPORT * Jonathan Dorfan Stanford Linear Accelerator Center, Stanford University, Stanford, CA 94309 USA For the SLAC, LBNL, LLNL PEP-II group Abstract The main design features of the PEP-II

More information

Status of CTF3. G.Geschonke CERN, AB

Status of CTF3. G.Geschonke CERN, AB Status of CTF3 G.Geschonke CERN, AB CTF3 layout CTF3 - Test of Drive Beam Generation, Acceleration & RF Multiplication by a factor 10 Drive Beam Injector ~ 50 m 3.5 A - 2100 b of 2.33 nc 150 MeV - 1.4

More information

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala) 2 Work Package and Work Unit descriptions 2.8 WP8: RF Systems (R. Ruber, Uppsala) The RF systems work package (WP) addresses the design and development of the RF power generation, control and distribution

More information

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation Matthias Liepe Assistant Professor of Physics Cornell University Experience with the Cornell ERL Injector SRF

More information

PEP-II Overview & Ramp Down Plan. J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007

PEP-II Overview & Ramp Down Plan. J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007 PEP-II Overview & Ramp Down Plan J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007 Topics Overview of the PEP-II Collider PEP-II turns off September 30, 2008. General list of components and buildings

More information

LCLS Injector Technical Review

LCLS Injector Technical Review LCLS Injector Technical Review Stanford Linear Accelerator Center November 3&4 2003 Review Committee Members: Prof. Patrick O Shea Chair University of Maryland Dr. E. Colby Stanford Linear Accelerator

More information

4.4 Injector Linear Accelerator

4.4 Injector Linear Accelerator 4.4 Injector Linear Accelerator 100 MeV S-band linear accelerator based on the components already built for the S-Band Linear Collider Test Facility at DESY [1, 2] will be used as an injector for the CANDLE

More information

Program Risks Risk Analysis Fallback Plans for the. John T. Seeman DOE PEP-II Operations Review April 26, 2006

Program Risks Risk Analysis Fallback Plans for the. John T. Seeman DOE PEP-II Operations Review April 26, 2006 Program Risks Risk Analysis Fallback Plans for the PEP-II B-FactoryB John T. Seeman DOE PEP-II Operations Review April 26, 2006 OPS Review Topics Are there any PEP-II program risks? Has the laboratory

More information

Beam-based Feedback Systems

Beam-based Feedback Systems Beam-based Feedback Systems Philip Burrows Queen Mary, University of London ILC Beam-based Feedback/Feedforward Systems Intra-train (bunch-bunch) feedback at IP: 3 MHz Pulse-pulse feedback at IP: 5 Hz

More information

Modulator Overview System Design vs. Tunnel Topologies. Snowmass Workshop August 16, 2005 Ray Larsen for the SLAC ILC Group

Modulator Overview System Design vs. Tunnel Topologies. Snowmass Workshop August 16, 2005 Ray Larsen for the SLAC ILC Group Modulator Overview System Design vs. Tunnel Topologies Snowmass Workshop August 16, 2005 Ray Larsen for the SLAC ILC Group Outline! I. Modulator Options vs. Topologies! II. Preliminary Cost Estimates!

More information

Summary of the 1 st Beam Line Review Meeting Injector ( )

Summary of the 1 st Beam Line Review Meeting Injector ( ) Summary of the 1 st Beam Line Review Meeting Injector (23.10.2006) 15.11.2006 Review the status of: beam dynamics understanding and simulations completeness of beam line description conceptual design of

More information

Design Studies For The LCLS 120 Hz RF Gun Injector

Design Studies For The LCLS 120 Hz RF Gun Injector BNL-67922 Informal Report LCLS-TN-01-3 Design Studies For The LCLS 120 Hz RF Gun Injector X.J. Wang, M. Babzien, I. Ben-Zvi, X.Y. Chang, S. Pjerov, and M. Woodle National Synchrotron Light Source Brookhaven

More information

Suggested ILC Beam Parameter Range Rev. 2/28/05 Tor Raubenheimer

Suggested ILC Beam Parameter Range Rev. 2/28/05 Tor Raubenheimer The machine parameters and the luminosity goals of the ILC were discussed at the 1 st ILC Workshop. In particular, Nick Walker noted that the TESLA machine parameters had been chosen to achieve a high

More information

!"!3

!!3 Abstract A single-mode 500 MHz superconducting cavity cryomodule has been developed at Cornell for the electronpositron collider/synchrotron light source CESR. The Cornell B-cell cavity belongs to the

More information

SABER A Facility for Accelerator Physics and Test Beam Experiments Roger Erickson SABER Workshop March 15, 2006

SABER A Facility for Accelerator Physics and Test Beam Experiments Roger Erickson SABER Workshop March 15, 2006 SABER A Facility for Accelerator Physics and Test Beam Experiments Roger Erickson SABER Workshop March 15, 2006 FFTB will soon be gone! The Problem: On April 10, 2006, the Final Focus Test Beam (FFTB)

More information

Pulses inside the pulse mode of operation at RF Gun

Pulses inside the pulse mode of operation at RF Gun Pulses inside the pulse mode of operation at RF Gun V. Vogel, V. Ayvazyan, K. Floettmann, D. Lipka, P. Morozov, H. Schlarb, S. Schreiber FLASH Seminar, DESY March 29, 2011 Contents Why we need a PiPmode

More information

Current status of XFEL/SPring-8 project and SCSS test accelerator

Current status of XFEL/SPring-8 project and SCSS test accelerator Current status of XFEL/SPring-8 project and SCSS test accelerator Takahiro Inagaki for XFEL project in SPring-8 inagaki@spring8.or.jp Outline (1) Introduction (2) Key technology for compactness (3) Key

More information

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting Status of BESSY II and berlinpro Wolfgang Anders Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting 16.-17.11.2016 at PSI Outline BESSY II Problems with circulators Landau cavity

More information

First Simultaneous Top-up Operation of Three Different Rings in KEK Injector Linac

First Simultaneous Top-up Operation of Three Different Rings in KEK Injector Linac First Simultaneous Top-up Operation of Three Different Rings in KEK Injector Linac Masanori Satoh (Acc. Lab., KEK) for the injector upgrade group 2010/9/16 1 Overview of Linac Beam Operation 2010/9/16

More information

J/NLC Progress on R1 and R2 Issues. Chris Adolphsen

J/NLC Progress on R1 and R2 Issues. Chris Adolphsen J/NLC Progress on R1 and R2 Issues Chris Adolphsen Charge to the International Linear Collider Technical Review Committee (ILC-TRC) To assess the present technical status of the four LC designs at hand,

More information

ILC RF System R&D. Chris Adolphsen, SLAC. Section of 1.3 GHz SC Linac. June 29, 2007 PAC07 Talk FRYC01

ILC RF System R&D. Chris Adolphsen, SLAC. Section of 1.3 GHz SC Linac. June 29, 2007 PAC07 Talk FRYC01 ILC RF System R&D Chris Adolphsen, SLAC June 29, 2007 PAC07 Talk FRYC01 Section of 1.3 GHz SC Linac ILC Main Linac RF Unit (1 of 560) RF System Gradient = 31.5 MV/m Rep Rate = 5 Hz Beam Current = 9.0 ma

More information

CLIC Feasibility Demonstration at CTF3

CLIC Feasibility Demonstration at CTF3 CLIC Feasibility Demonstration at CTF3 Roger Ruber Uppsala University, Sweden, for the CLIC/CTF3 Collaboration http://cern.ch/clic-study LINAC 10 MO303 13 Sep 2010 The Key to CLIC Efficiency NC Linac for

More information

SLAC R&D Program for a Polarized RF Gun

SLAC R&D Program for a Polarized RF Gun ILC @ SLAC R&D Program for a Polarized RF Gun SLAC-PUB-11657 January 2006 (A) J. E. CLENDENIN, A. BRACHMANN, D. H. DOWELL, E. L. GARWIN, K. IOAKEIMIDI, R. E. KIRBY, T. MARUYAMA, R. A. MILLER, C. Y. PRESCOTT,

More information

SRS and ERLP developments. Andrew moss

SRS and ERLP developments. Andrew moss SRS and ERLP developments Andrew moss Contents SRS Status Latest news Major faults Status Energy Recovery Linac Prototype Latest news Status of the RF system Status of the cryogenic system SRS Status Machine

More information

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR Proceedings of FEL213, New York, NY, USA STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR F. Loehl, J. Alex, H. Blumer, M. Bopp, H. Braun, A. Citterio, U. Ellenberger, H. Fitze, H. Joehri, T. Kleeb, L.

More information

Linac 4 Instrumentation K.Hanke CERN

Linac 4 Instrumentation K.Hanke CERN Linac 4 Instrumentation K.Hanke CERN CERN Linac 4 PS2 (2016?) SPL (2015?) Linac4 (2012) Linac4 will first inject into the PSB and then can be the first element of a new LHC injector chain. It will increase

More information

ATF2 project in the ATF international collaboration, including coordination issues

ATF2 project in the ATF international collaboration, including coordination issues ATF2 project in the ATF international collaboration, including coordination issues 1. Status of ATF collaboration 2. R&D items in ATF 3. Schedule 4. Expectation Junji Urakawa, KEK ATF2-IN2P3-KEK kick-off

More information

Overview of NLC/JLC Collaboration *

Overview of NLC/JLC Collaboration * SLAC PUB 10117 August 2002 Overview of NLC/JLC Collaboration * K. Takata KEK, Oho, Tsukuba-shi 305-0801, JAPAN On behalf of the NLC Group Stanford Linear Accelerator Center, Stanford, California 94309,

More information

TTF / VUV-FEL. Schedule 2005 and Project Management Issues. Schedule 2005 Project Organisation Budget & Controlling

TTF / VUV-FEL. Schedule 2005 and Project Management Issues. Schedule 2005 Project Organisation Budget & Controlling TTF / VUV-FEL Schedule 200 and Project Management Issues Schedule 200 Project Organisation Budget & Controlling Hans Weise / DESY DESY MAC Meeting November 9th, 2004 TTF Linac Start-up After Final Installation

More information

Activities on FEL Development and Application at Kyoto University

Activities on FEL Development and Application at Kyoto University Activities on FEL Development and Application at Kyoto University China-Korea-Japan Joint Workshop on Electron / Photon Sources and Applications Dec. 2-3, 2010 @ SINAP, Shanghai Kai Masuda Inst. Advanced

More information

PEP-II IR-2 Alignment

PEP-II IR-2 Alignment SLAC-PUB-10328 January 2004 PEP-II IR-2 Alignment A. Seryi, S. Ecklund, C. Le Cocq, R. Pushor, R. Ruland, Z. Wolf SLAC, Stanford, CA 94025, USA This paper describes the first results and preliminary analysis

More information

North Damping Ring RF

North Damping Ring RF North Damping Ring RF North Damping Ring RF Outline Overview High Power RF HVPS Klystron & Klystron EPICS controls Cavities & Cavity Feedback SCP diagnostics & displays FACET-specific LLRF LLRF distribution

More information

POLARIZED LIGHT SOURCES FOR PHOTOCATHODE ELECTRON GUNS AT SLAC?

POLARIZED LIGHT SOURCES FOR PHOTOCATHODE ELECTRON GUNS AT SLAC? SLAC-PUB-5965 December 1992 (4 POLARIZED LIGHT SOURCES FOR PHOTOCATHODE ELECTRON GUNS AT SLAC? M. Woods,O J. Frisch, K. Witte, M. Zolotorev Stanford Linear Accelerator Center Stanford University, Stanford,

More information

Status of SOLARIS Arkadiusz Kisiel

Status of SOLARIS Arkadiusz Kisiel Status of SOLARIS Arkadiusz Kisiel Solaris National Synchrotron Light Source Jagiellonian University Czerwone Maki 98 30-392 Kraków www.synchrotron.uj.edu.pl Arkadiusz.Kisiel@uj.edu.pl On behalf of SOLARIS

More information

Status of RF Power and Acceleration of the MAX IV - LINAC

Status of RF Power and Acceleration of the MAX IV - LINAC Status of RF Power and Acceleration of the MAX IV - LINAC Dionis Kumbaro ESLS RF Workshop 2015 MAX IV Laboratory A National Laboratory for synchrotron radiation at Lunds University 1981 MAX-lab is formed

More information

New Filling Pattern for SLS-FEMTO

New Filling Pattern for SLS-FEMTO SLS-TME-TA-2009-0317 July 14, 2009 New Filling Pattern for SLS-FEMTO Natalia Prado de Abreu, Paul Beaud, Gerhard Ingold and Andreas Streun Paul Scherrer Institut, CH-5232 Villigen PSI, Switzerland A new

More information

reported by T. Shintake KEK / RIKEN Japan Summary of C-band R&D for Linear Collider at KEK New soft-x-ray FEL Project at RIKEN/SPring-8

reported by T. Shintake KEK / RIKEN Japan Summary of C-band R&D for Linear Collider at KEK New soft-x-ray FEL Project at RIKEN/SPring-8 C-band RF System R&D reported by T. Shintake KEK / RIKEN Japan Summary of C-band R&D for Linear Collider at KEK New soft-x-ray FEL Project at RIKEN/SPring-8 Project was funded in 2001 April Material Science

More information

Upgrading LHC Luminosity

Upgrading LHC Luminosity 1 Upgrading LHC Luminosity 2 Luminosity (cm -2 s -1 ) Present (2011) ~2 x10 33 Beam intensity @ injection (*) Nominal (2015?) 1 x 10 34 1.1 x10 11 Upgraded (2021?) ~5 x10 34 ~2.4 x10 11 (*) protons per

More information

Status of the FAIR Project. Jürgen Henschel FAIR Project Leader / Technical Director GSI & FAIR

Status of the FAIR Project. Jürgen Henschel FAIR Project Leader / Technical Director GSI & FAIR Status of the FAIR Project Jürgen Henschel FAIR Project Leader / Technical Director GSI & FAIR Finland France Germany India Poland Romania Russia Slovenia Sweden UK FAIR Strategic objectives FAIR phase

More information

Requirements for the Beam Abort Magnet and Dump

Requirements for the Beam Abort Magnet and Dump Requirements for the Beam Abort Magnet and Dump A beam abort kicker (pulsed dipole magnet) and dump are required upbeam of the LCLS undulator in order to protect the undulator from mis-steered and poor

More information

Evaluation of Performance, Reliability, and Risk for High Peak Power RF Sources from S-band through X-band for Advanced Accelerator Applications

Evaluation of Performance, Reliability, and Risk for High Peak Power RF Sources from S-band through X-band for Advanced Accelerator Applications Evaluation of Performance, Reliability, and Risk for High Peak Power RF Sources from S-band through X-band for Advanced Accelerator Applications Michael V. Fazio C. Adolphsen, A. Jensen, C. Pearson, D.

More information

X-Band Klystron Development at

X-Band Klystron Development at X-Band Klystron Development at SLAC Slide 1 The Beginning X-band klystron work began at SLAC in the mid to late 80 s to develop high frequency (4x SLAC s-band), high power RF sources for the linear collider

More information

FINAL DESIGN OF ILC RTML EXTRACTION LINE FOR SINGLE STAGE BUNCH COMPRESSOR

FINAL DESIGN OF ILC RTML EXTRACTION LINE FOR SINGLE STAGE BUNCH COMPRESSOR BNL-94942-2011-CP FINAL DESIGN OF ILC RTML EXTRACTION LINE FOR SINGLE STAGE BUNCH COMPRESSOR S. Sletskiy and N. Solyak Presented at the 2011 Particle Accelerator Conference (PAC 11) New York, NY March

More information

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems LCLS RF Reference and Control R. Akre Last Update 5-19-04 Sector 0 RF and Timing Systems The reference system for the RF and timing starts at the 476MHz Master Oscillator, figure 1. Figure 1. Front end

More information

CLEX (CLIC Experimental Area)

CLEX (CLIC Experimental Area) CLEX (CLIC Experimental Area) Status and plans G.Geschonke for Hans Braun CERN CT3 coll meetg 2005 CLEX 1 CT3 objectives R1.1 CLIC accelerating structure, R1.2 rive beam scheme with a fully loaded linac

More information

Challenges in Accelerator Beam Instrumentation

Challenges in Accelerator Beam Instrumentation Proceedings of the DPF-2009 Conference, Detroit, MI, July 27-31, 2009 1 Challenges in Accelerator Beam Instrumentation M. Wendt Fermi National Accelerator Laboratory, Batavia, IL 60510, USA The challenges

More information

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY A. Wheelhouse ASTeC, STFC Daresbury Laboratory ESLS XVIII Workshop, ELLETRA 25 th 26 th November 2010 Contents Brief Description ALICE

More information

ANKA Status Report. N.Smale, A.-S. Müller, E. Huttel, M.Schuh Slides courtesy of A.-S. Müller and C.Heske.

ANKA Status Report. N.Smale, A.-S. Müller, E. Huttel, M.Schuh Slides courtesy of A.-S. Müller and C.Heske. ANKA Status Report N.Smale, A.-S. Müller, E. Huttel, M.Schuh Slides courtesy of A.-S. Müller and C.Heske. KIT - University of the State of Baden-Wuerttemberg and National Laboratory of the Helmholtz Association

More information

PEP-II Disassembly Technical Systems

PEP-II Disassembly Technical Systems PEP-II Disassembly Technical Systems PEP-II D&D Review 6-Aug-2007 S.DeBarger S.Ecklund, A.Hill, D.Kharakh, M.Zurawel Outline Project safety Disassembly of technical systems Shielding Vac/Mechanical Cable

More information

A New High Intensity Proton Source. The SCRF Proton Driver. (and more!) at Fermilab. July 15, Bill Foster SRF2005

A New High Intensity Proton Source. The SCRF Proton Driver. (and more!) at Fermilab. July 15, Bill Foster SRF2005 The SCRF Proton Driver A New High Intensity Proton Source (and more!) at Fermilab Bill Foster SRF2005 July 15, 2005 Outline The Concept Fermilab Strategic Context Proton Driver SRF Linac Design Ferrite

More information

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project Workshop on the future and next generation capabilities of accelerator driven neutron and muon sources

More information

30 GHz Power Production / Beam Line

30 GHz Power Production / Beam Line 30 GHz Power Production / Beam Line Motivation & Requirements Layout Power mode operation vs. nominal parameters Beam optics Achieved performance Problems Beam phase switch for 30 GHz pulse compression

More information

News from HZB / BESSY Wolfgang Anders at ESLS-RF Meeting September 2010 Trieste

News from HZB / BESSY Wolfgang Anders at ESLS-RF Meeting September 2010 Trieste News from HZB / BESSY Wolfgang Anders at ESLS-RF Meeting September 2010 Trieste Outline Status Klystrons / IOT Modifications of transmitters New LINAC for BESSY II Status BERLinPro HoBiCaT Extension --

More information

ESS Linac WP8 Radio Frequency Systems and Test Facilities

ESS Linac WP8 Radio Frequency Systems and Test Facilities ESS Linac WP8 Radio Frequency Systems and Test Facilities ESS TAC Lund, 8 July 2010 Roger Ruber (Uppsala University) for the ESS Linac RF Team Outline Work Package description Objectives Organization Technical

More information

PROJECT DESCRIPTION. Longitudinal phase space monitors for the ILC injectors and bunch compressors

PROJECT DESCRIPTION. Longitudinal phase space monitors for the ILC injectors and bunch compressors PROJECT DESCRIPTION Longitudinal phase space monitors for the ILC injectors and bunch compressors Personnel and Institution(s) requesting funding Philippe Piot Northern Illinois University Dept of Physics,

More information

Digital BPMs and Orbit Feedback Systems

Digital BPMs and Orbit Feedback Systems Digital BPMs and Orbit Feedback Systems, M. Böge, M. Dehler, B. Keil, P. Pollet, V. Schlott Outline stability requirements at SLS storage ring digital beam position monitors (DBPM) SLS global fast orbit

More information

Top-Up Experience at SPEAR3

Top-Up Experience at SPEAR3 Top-Up Experience at SPEAR3 Contents SPEAR 3 and the injector Top-up requirements Hardware systems and modifications Safety systems & injected beam tracking Interlocks & Diagnostics SPEAR3 Accelerator

More information

Photoinjector Laser Operation and Cathode Performance

Photoinjector Laser Operation and Cathode Performance Photoinjector Laser Operation and Cathode Performance Daniele Sertore, INFN Milano LASA Siegfried Schreiber, DESY Laser operational experience Laser beam properties Cathode performances Outlook TTF and

More information

CONSTRUCTION AND COMMISSIONING OF BEPCII

CONSTRUCTION AND COMMISSIONING OF BEPCII Abstract CONSTRUCTION AND COMMISSIONING OF BEPCII C. Zhang, J.Q. Wang, L. Ma and G.X.Pei for the BEPCII Team, IHEP, CAS P.O.Box 918, Beijing 100049, China BEPCII is the major upgrade of BEPC (Beijing Electron-

More information

The X-Ray FEL at DESY

The X-Ray FEL at DESY The X-Ray FEL at DESY Hans Weise / DESY TESLA The Superconducting Electron- Positron Linear Collider with an Integrated X-Ray Laser Laboratory Technical Design Report March 2001 integrated into TESLA LC:

More information

High Rep Rate Guns: FZD Superconducting RF Photogun

High Rep Rate Guns: FZD Superconducting RF Photogun High Rep Rate Guns: FZD Superconducting RF Photogun J. Teichert, A. Arnold, H. Büttig, D. Janssen, M. Justus, U. Lehnert, P. Michel, K. Moeller, P. Murcek, Ch. Schneider, R. Schurig, G. Staats, F. Staufenbiel,

More information

2008 JINST 3 S LHC Machine THE CERN LARGE HADRON COLLIDER: ACCELERATOR AND EXPERIMENTS. Lyndon Evans 1 and Philip Bryant (editors) 2

2008 JINST 3 S LHC Machine THE CERN LARGE HADRON COLLIDER: ACCELERATOR AND EXPERIMENTS. Lyndon Evans 1 and Philip Bryant (editors) 2 PUBLISHED BY INSTITUTE OF PHYSICS PUBLISHING AND SISSA RECEIVED: January 14, 2007 REVISED: June 3, 2008 ACCEPTED: June 23, 2008 PUBLISHED: August 14, 2008 THE CERN LARGE HADRON COLLIDER: ACCELERATOR AND

More information

TITLE PAGE. Title of paper: PUSH-PULL FEL, A NEW ERL CONCEPT Author: Andrew Hutton. Author Affiliation: Jefferson Lab. Requested Proceedings:

TITLE PAGE. Title of paper: PUSH-PULL FEL, A NEW ERL CONCEPT Author: Andrew Hutton. Author Affiliation: Jefferson Lab. Requested Proceedings: TITLE PAGE Title of paper: PUSH-PULL FEL, A NEW ERL CONCEPT Author: Andrew Hutton Author Affiliation: Jefferson Lab Requested Proceedings: Unique Session ID: Classification Codes: Keywords: Energy Recovery,

More information