6MSD Weekly Scheduling Meeting. 1:30, MCC Conference Room

Size: px
Start display at page:

Download "6MSD Weekly Scheduling Meeting. 1:30, MCC Conference Room"

Transcription

1 6MSD Weekly Scheduling Meeting 1:30, MCC Conference Room July 6, ) Glance Back and 2-Week Look Ahead (F. Pilat) mins 2) PMI Report (P. Collins)... 5 mins 3) Critical Path Service Provider Reports mins (a) Alignment (Curtis) (b) Magnet Refurbishment (Baggett) (c) Installation/Alignment (Wilson) (d) HPRF (Kimber) 4) Halls Status Report (E. Folts)... 5 mins 5) Special Topics: None... 0 mins 6) Safety Report (M. Logue)... 5 mins 7) Meeting Recap and Action Items (All)... 5 mins

2 6MSD: Glance back & look ahead Fulvia Pilat 6MSD Meeting July 6, 2011

3 Outline Progress last week No Change Control Board meeting this week Lookout next 4 weeks Hot topics

4 Progress Wed June 29 - Wed July 6 Weeks: 8 down, 19 to go Highlights: Removal of Arc 7 9 magnets in the East Arc Magnet re work also focusing on the East Arc RF installation C100 leaks fixed, ready for cool down again FEL ¼ cryomodule also ready for cool down Cyber security attack: minimal impact on 6MSD activities so far Impact on magnet measurements?

5 4 weeks look ahead Still, potential decision point to rework Arc 5 Complete removal/rework/installation magnets WA and EA Arc 7 and 9 RFinstallation & testing LCW upgrades Civil work Phase 3, tunnel extension, photon beam pipe, BSY building. Continue LCW, work on tunnel extension and photon beam pipe Peppo installation Halls Facilities: TEDF, PSS, repair FEL stairs, maintenance

6 4 week look ahead hot topics CRYOMODULES C100 production and installation schedule Micro phonics Task force : results data analysis +engineering solutions Impact on 12 GeV Project plans Installation and operations of R100 and Admiral Meeting to discuss and define a plan. Civil Phase 3 nominal 8 days delay on schedule, probably 2 5 days in reality, effort in place to minimize delays (impact on PSS certs, start up with beam)

7 PM&IP 6MSD 7/06/11 Weekly Progress Meeting (7/01/11 Data) Report #8

8 PM&IP Schedule Issues: Hall D Phase 3 Tunnel Extension is ~5 Days behind schedule. Cryomodules??? Resource issues: None at this time.

9 PM&IP Other Schedule Information at Four Week Look Ahead - Shows all activities that have started that are not complete and any activities due to start in the next four weeks Critical Path Shows all MUST activities that have 2 days or less float. Schedule Variance - Shows all MUST activities that are not 100% complete and that the Start/Finish dates have slipped by at least 5 days.

10 Shutdown Work Summary Organization: Alignment Name: Chris Curtis Date: 6th July, 2011 Last Week Work That Went Better Than / As Expected: Step 2A of west arc dipoles continued 2 more stacks & XP dipoles. HD Ice warm fiducialization completed. G2p FZ dipoles fiducialized; Target magnet reference grid measured. C100 2 cryomodule fiducialized. Hall A spectrometers surveyed. Work That Went Slower Than Expected, Delays, and Issues: Ongoing Shutdown Work Table 1: Next Week's Work ( green = no concerns; yellow = some concerns; red = serious concerns) Project & Customer Status Completion Tasks Comments/Concerns 12 Gev Arcs X TBD Alignment of re installed dipoles in west and east arcs. Arc 10 Magnets X Opportunistic Quad and dipole Step 2A alignment. Hall A G2P X TBD Slow Raster, Calorimeter & FZ1 Step 2A survey. FZ2 stand? 12 Gev Civil Hall D X July Check elevation & location of tunnel extension floor. 6MSD weekly mtg Align Jul 06 Page 1 of 2 Will be switching between west arc step 2B and east arc step 2A. Continuing. Grouting completed today. Survey Thursday/ Friday. Starting today. Ground motion near excavation expected.

11 Table 2: Other Upcoming Work ( green = no concerns; yellow = some concerns; red = serious concerns) Project & Customer Status Completion Tasks Comments/Concerns 12 GeV Arcs X TBD Dipole re alignment. Full steam ahead on west and east arcs for the next 3 4 weeks. Ongoing New Work Requests Requiring Schedule Changes: Nothing significant Permits Not Already in Hand (hot work, lifting, blind penetrations): None Significant Problems Pending (delays, technical issues, resource issues, scheduling): None Staffing Outlook: OK; small chance of needing to run 3 rd crew. 6MSD weekly mtg Align Jul 06 Page 2 of 2

12 Organization: Magnet Measurement Name: Ken Baggett Date: July 06, 2011 Last Week Shutdown Work Summary Work That Went Better Than Expected: Magnet Removal South EA removal complete. North EA removal ½ complete. Magnet Refurbishment EA. ~ ½ the southeast arc (7,9) refurbished Second test stand working. Work That Went Slower Than Expected, Delays, and Issues: Communication problems with power supplies as a result of the cyber event. Problem fixed but caused a 1/2 day delay. Thanks to Pam Kjeldsen, Scott Windham, Anthony Cuffe, and Brian Hess for their prompt attention to get the problem fixed. Ongoing Shutdown Work Table 1: Next Week's Work Project & Customer 12GeV 12GeV 12GeV 12GeV Status x x x x k ( green = no concerns; yellow = some concerns; red = serious concerns) Completion July 7 (EA ongoing ongoing ongoing Tasks 7,9) Remove Stacks Refurbish Stacks Measure Stacks Re install Stacks Comments/Concerns EA EA 9 13 EA 9 13 (part) MMF_July 06_2011 Page 1 of 4

13 Table 2: Other Upcoming Work ( green = no concerns; yellow = some concerns; red = serious concerns) Project & Customer Status Completion Tasks Comments/Concerns Injector x July Map 2 magnets Can push out to August after 12GeV mapping completed. Injector X July 8 Solenoid May do additional mapping if needed New Work Requests Requiring Schedule Changes: None Permits Not Already in Hand (hot work, lifting, blind penetrations): None Significant Problems Pending (delays, technical issues, resource issues, scheduling): None Staffing Outlook: Appropriate to meet schedule MMF_July_06_2011 Page 2 of 4

14 MMF_July_06_2011 Page 3 of 4

15 MMF_July_06_2011 Page 4 of 4

16 Shutdown Work Summary Organization: MSINST Name: Neil Wilson Date: 7/6/11 Last Week Work That Went Better Than Expected/Completed: 6 Girders Installed in Arc 10. Note: All dipoles & girders installed that can be in the 1 st 1/2 of the west arc Disconnected East Arc 7&9 Dipoles, Vacuum, LCW & Power. Fabricating & Pressure Testing Manifolds for Klystron Racks & CPS s SL24 FEL Leak Checking & Vacuum Support. Pressure Test of SAB PS LCW Header. Work That Went Slower Than Expected, Delays, and Issues: West Arc SLM awaiting parts. We will pump down for Leak Checking, Vent up this section when parts are available ( 30 days). Pump back down & leak check that section. Ongoing Shutdown Work Table 1: Next Week's Work Project & Customer 12GeV 12GeV 12GeV G2P 12GeV Status X X X X X k ( green = no concerns; yellow = some concerns; red = serious concerns) Completion 7/1 Tasks Cartridge & Stem Work SAB LCW Upgrade Dipole Hook Up Vac & LCW Stand Installation Fabricating Headers for Klystron Racks & CPS s SL25 Comments/Concerns On Going East Arc On Going East & West Arc On Going Awaiting Manifolds Wee ekly Report 1 Page 1 of 3

17 Project & Customer Status Completion Tasks Comments/Concerns 12GeV X Arc 10 Dipole & Girder Installation On Going Hall D X LCW Piping Installation Awaiting Mat l Delivery 12GeV X Install SL26 CPS Delivery delayed Expected 7/7 or 8 12GeV 7/8 Pump Down & Leak Check South 1/2 of West Arc 6GeV X Swapping Out Vacuum Valves On Going Hall C X Moeller Vac. Work Venting FEL X Vacuum Support On Going 6GeV X Ion Pump Replacement On Going Table 2: Other Upcoming Work ( green = no concerns; yellow = some concerns; red = serious concerns) Project & Customer Status Completion Tasks Comments/Concerns 12GeV X Dipole Hook Up LCW & Vac West Arc North 1/2 12GeV & PPEPo X Fill Pene. NL24 & Inj. Awaiting PEPPo Cable Pulls 12GeV X Fabricating Headers for Klystron Awaiting Manifolds Racks & CPS s G2P X Stand Installation 6GeV X Vacuum Valve Limit Switch Replacement 6GeV X Vac. Turbo Pmp. Maint New Work Requests Requiring Schedule Changes: None Permits Not Already in Hand (hot work, lifting, blind penetrations): None Significant Problems Pending (delays, technical issues, resource issues, scheduling): None Weekly Report 1 Page 2 of 3

18 Staffing Outlook: OK Weekly Report 1 Page 3 of 3

19 Shutdown Work Summary Organization: HPRF Name: Andrew Kimber Date: 6 July 2011 Last Week Work That Went Better Than/As Expected: General cabling progresses final connections being made this week LLRF firmware is ready for testing with HPRF Temporary water hosess delivered and installed Work That Went Slower Than Expected, Delays, and Issues: 3 Klystrons installed, 6 now in place Water manifolds/piping installed. Hoses in progress. Ongoing Shutdown Work Table 1: Next Week's Work Project & Customer 12GeV HPRF 12GeV HPRF 12GeV HPRF Mech Tech Status x x x x k ( green = no concerns; yellow = some concerns; red = serious concerns) Completion 7/6/11 7/7/11 7/8/11 7/8/11 Tasks LCW hoses Solenoid/Klystron install General cabling CPS #5 install Comments/Concerns 6 installed, 2 tested awaiting install Final connections to CPS, last 2 klystronss In zone 2L26, delivery expected Fri/Mon (delayed 1 week) Shutdown Wo ork Summary AJK 06JUL11 Page 1 of 3

20 Table 2: Other Upcoming Work ( green = no concerns; yellow = some concerns; red = serious concerns) Project & Customer Status Completion Tasks Comments/Concerns 12GeV HPRF x 7/22/11 Test into shorts complete 12GeV HPRF x Late July Continue installation of 2L25 A lot of tasks will be completed early New Work Requests Requiring Schedule Changes: n/a Permits Not Already in Hand (hot work, lifting, blind penetrations): n/a Significant Problems Pending (delays, technical issues, resource issues, scheduling): Possible option for the R100: Placing it in 2L25 for waveguide measurements Chris will attempt to get the measurements virtually from C Staffing Outlook: good Shutdown Work Summary AJK 06JUL11 Page 2 of 3

21 Zone 2L24, as of 06 July 2011 Shutdown Work Summary AJK 06JUL11 Page 3 of 3

22

23

24

25

26

27 G2P Target installation and Beyond

28 How it looks now

29 Installed

30 How it looks now

31 Going in Slow raster

32 How it looks now

33 Going in Chicane after

34 Chicane power supply and equipment area

35

36 Questions?

37 Good Day! First Aid Injury *Click on symbol in calendar for details Recordable Injury *Click on symbol in calendar for details Project to Date: First Aid: 7 Recordable: 1 DART: 1 Other Noteworthy Events *Click on symbol in calendar for details

38 July 2011 Events Date Location Event 07/01/11 Hall D Construction Site Subcontractor was struck on hard hat with a 2 foot hollow metal spackling rod. Subcontractor was evaluated by JLab Occupational Health Nurse and no treatment was rendered. Subcontractor returned to work with no restrictions.

6MSD Weekly Scheduling Meeting. 1:30, MCC Conference Room

6MSD Weekly Scheduling Meeting. 1:30, MCC Conference Room 6MSD Weekly Scheduling Meeting Wednesday @ 1:30, MCC Conference Room July 27, 2011 1) Glance Back and 2-Week Look Ahead (W. Oren)... 10 mins 2) PMI Report (P. Collins)... 5 mins 3) Critical Path Service

More information

6MSD Weekly Scheduling Meeting. 1:30, MCC Conference Room

6MSD Weekly Scheduling Meeting. 1:30, MCC Conference Room 6MSD Weekly Scheduling Meeting Wednesday @ 1:30, MCC Conference Room August 24, 2011 1) Glance Back and 2-Week Look Ahead (F. Pilat)... 10 mins 2) PMI Report (P. Collins)... 5 mins 3) Critical Path Service

More information

LSD Bi-Weekly Resource Planning Meeting Agenda 25 July 2012

LSD Bi-Weekly Resource Planning Meeting Agenda 25 July 2012 LSD Bi-Weekly Resource Planning Meeting Agenda 25 July 2012 Glance Back / 2-Week Look Ahead / Change-Control Board (CCB) Report (10 min) F. Pilat Safety Report (5 min) M. Logue Special Topic (5 min) Puddles

More information

LSD Review December 2012 Schedule, Re-Baseline, & Resource Analysis

LSD Review December 2012 Schedule, Re-Baseline, & Resource Analysis LSD Review December 2012 Schedule, Re-Baseline, & Resource Analysis Dianne Napier Outline Part II Review Charges Addressed in this Presentation: Issues raised in Part I Review Report adequately addressed

More information

Operating Experience and Reliability Improvements on the 5 kw CW Klystron at Jefferson Lab

Operating Experience and Reliability Improvements on the 5 kw CW Klystron at Jefferson Lab Operating Experience and Reliability Improvements on the 5 kw CW Klystron at Jefferson Lab Richard Walker & Richard Nelson Jefferson Lab, Newport News VA Jefferson Lab is a $600M Department of Energy facility

More information

AREAL- Phase 1. B. Grigoryan on behalf of AREAL team

AREAL- Phase 1. B. Grigoryan on behalf of AREAL team AREAL- Phase 1 Progress & Status B. Grigoryan on behalf of AREAL team Contents Machine Layout Building & Infrastructure Laser System RF System Vacuum System Cooling System Control System Beam Diagnostics

More information

RF Upgrades & Experience At JLab. Rick Nelson

RF Upgrades & Experience At JLab. Rick Nelson RF Upgrades & Experience At JLab Rick Nelson Outline Background: CEBAF / Jefferson Lab History, upgrade requirements & decisions Progress & problems along the way Present status Future directions & concerns

More information

Upgrade of CEBAF to 12 GeV

Upgrade of CEBAF to 12 GeV Upgrade of CEBAF to 12 GeV Leigh Harwood (for 12 GeV Accelerator team) Page 1 Outline Background High-level description Schedule Sub-system descriptions and status Summary Page 2 CEBAF Science Mission

More information

Monthly Progress Report Stanford Synchrotron Radiation Laboratory

Monthly Progress Report Stanford Synchrotron Radiation Laboratory Monthly Progress Report Stanford Synchrotron Radiation Laboratory April 2003 TABLE OF CONTENTS A. Project Summary 1. Technical Progress 3 2. Cost Data 5 B. Design and Fabrication Reports 1.1 Magnets &

More information

Availability and Reliability Issues for the ILC

Availability and Reliability Issues for the ILC Availability and Reliability Issues for the ILC SLAC Presented at PAC07 26 June 07 Contents Introduction and purpose of studies The availability simulation What was modeled (important assumptions) Some

More information

PEP-II Overview & Ramp Down Plan. J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007

PEP-II Overview & Ramp Down Plan. J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007 PEP-II Overview & Ramp Down Plan J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007 Topics Overview of the PEP-II Collider PEP-II turns off September 30, 2008. General list of components and buildings

More information

P. Emma, et al. LCLS Operations Lectures

P. Emma, et al. LCLS Operations Lectures P. Emma, et al. LCLS Operations Lectures LCLS 1 LCLS Accelerator Schematic 6 MeV 135 MeV 250 MeV σ z 0.83 mm σ z 0.83 mm σ z 0.19 mm σ δ 0.05 % σ δ 0.10 % σ δ 1.6 % Linac-0 L =6 m rf gun L0-a,b Linac-1

More information

HD Review March 30, 2011 Franz Klein

HD Review March 30, 2011 Franz Klein HD Review March 30, 2011 Franz Klein !! Circularly & linearly polarized photon beam on longitudinally polarized target Circularly polar. photon via helicity transfer from 92 calendar days Linearly polar.

More information

RF Power Upgrade at Jefferson Lab

RF Power Upgrade at Jefferson Lab RF Power Upgrade at Jefferson Lab Rick Nelson*, Andrew Kimber *nelson@jlab.org * Notice: Authored by Jefferson Science Associates, LLC under U.S. DOE Contract No. DE- AC05-06OR23177. The U.S. Government

More information

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project Workshop on the future and next generation capabilities of accelerator driven neutron and muon sources

More information

Hall-B Beamline Commissioning Plan for CLAS12

Hall-B Beamline Commissioning Plan for CLAS12 Hall-B Beamline Commissioning Plan for CLAS12 Version 1.5 S. Stepanyan December 19, 2017 1 Introduction The beamline for CLAS12 utilizes the existing Hall-B beamline setup with a few modifications and

More information

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline 3 cerl 3-1 cerl Overview As described before, the aim of the cerl in the R&D program includes the development of critical components for the ERL, as well as the construction of a test accelerator. The

More information

Upgrading LHC Luminosity

Upgrading LHC Luminosity 1 Upgrading LHC Luminosity 2 Luminosity (cm -2 s -1 ) Present (2011) ~2 x10 33 Beam intensity @ injection (*) Nominal (2015?) 1 x 10 34 1.1 x10 11 Upgraded (2021?) ~5 x10 34 ~2.4 x10 11 (*) protons per

More information

12GeV CEBAF Commissioning

12GeV CEBAF Commissioning 12GeV CEBAF Commissioning Operations Dept. Accelerator Division JLAB Outline 1 Process Integrated Process Overview Accelerator Readiness Review Process Internal Reviews/Process Process Recap 2 Beam Commissioning

More information

Program Risks Risk Analysis Fallback Plans for the. John T. Seeman DOE PEP-II Operations Review April 26, 2006

Program Risks Risk Analysis Fallback Plans for the. John T. Seeman DOE PEP-II Operations Review April 26, 2006 Program Risks Risk Analysis Fallback Plans for the PEP-II B-FactoryB John T. Seeman DOE PEP-II Operations Review April 26, 2006 OPS Review Topics Are there any PEP-II program risks? Has the laboratory

More information

Summer / Fall 2004 Downtime AEG Preparation Work

Summer / Fall 2004 Downtime AEG Preparation Work Summer / Fall 2004 Downtime AEG Preparation Work In general the Alignment Engineering Group consulted with individuals involved in many of the scheduled downtime activities. Equipment was checked, manpower

More information

SABER A Facility for Accelerator Physics and Test Beam Experiments Roger Erickson SABER Workshop March 15, 2006

SABER A Facility for Accelerator Physics and Test Beam Experiments Roger Erickson SABER Workshop March 15, 2006 SABER A Facility for Accelerator Physics and Test Beam Experiments Roger Erickson SABER Workshop March 15, 2006 FFTB will soon be gone! The Problem: On April 10, 2006, the Final Focus Test Beam (FFTB)

More information

SRS and ERLP developments. Andrew moss

SRS and ERLP developments. Andrew moss SRS and ERLP developments Andrew moss Contents SRS Status Latest news Major faults Status Energy Recovery Linac Prototype Latest news Status of the RF system Status of the cryogenic system SRS Status Machine

More information

CEBAF Accelerator Update. Michael Tiefenback CASA Accelerator Physics Experimental Liaison June 14, 2017

CEBAF Accelerator Update. Michael Tiefenback CASA Accelerator Physics Experimental Liaison June 14, 2017 CEBAF Accelerator Update Michael Tiefenback CASA Accelerator Physics Experimental Liaison June 14, 2017 CLAS12 Collaboration Meeting, June 13-16, 2017 1 Accelerator Division Leadership On April 30 Andrew

More information

Beam Losses During LCLS Injector Phase-1 1 Operation

Beam Losses During LCLS Injector Phase-1 1 Operation Beam Losses During LCLS Injector Phase-1 1 Operation & Paul Emma September 28, 2006 Radiation Safety Committee Review Scope of Phase 1 Operation Request for Three Operating Modes Operating Plan for Phase

More information

STATUS OF THE SwissFEL C-BAND LINAC

STATUS OF THE SwissFEL C-BAND LINAC STATUS OF THE SwissFEL C-BAND LINAC F. Loehl, J. Alex, H. Blumer, M. Bopp, H. Braun, A. Citterio, U. Ellenberger, H. Fitze, H. Joehri, T. Kleeb, L. Paly, J.-Y. Raguin, L. Schulz, R. Zennaro, C. Zumbach,

More information

Extraction/Separator Setup. Michael Spata Operations Stay Treat July 16, 2015

Extraction/Separator Setup. Michael Spata Operations Stay Treat July 16, 2015 Extraction/Separator Setup Michael Spata Operations Stay Treat July 16, 2015 Accelerator Overview Extraction System Design settings for magnets and RF Separators come from CED All beamlines have been commissioned

More information

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation Matthias Liepe Assistant Professor of Physics Cornell University Experience with the Cornell ERL Injector SRF

More information

PEP-II Disassembly Technical Systems

PEP-II Disassembly Technical Systems PEP-II Disassembly Technical Systems PEP-II D&D Review 6-Aug-2007 S.DeBarger S.Ecklund, A.Hill, D.Kharakh, M.Zurawel Outline Project safety Disassembly of technical systems Shielding Vac/Mechanical Cable

More information

Energy Upgrade Options for the LCLS-I Linac

Energy Upgrade Options for the LCLS-I Linac Energy Upgrade Options for the LCLS-I Linac LCLS-II TN-14-10 11/12/2014 John Sheppard, F.J. Decker, R. Iverson, H.D. Nuhn, M. Sullivan, J. Turner November 18, 2014 LCLSII-TN-14-07 LCLS 1 Linac Energy Increase

More information

5 Project Costs and Schedule

5 Project Costs and Schedule 93 5 Project Costs and Schedule 5.1 Overview The cost evaluation for the integrated version of the XFEL with 30 experiments and 35 GeV beam energy as described in the TDR-2001 yielded 673 million EUR for

More information

Status of the FAIR Project. Jürgen Henschel FAIR Project Leader / Technical Director GSI & FAIR

Status of the FAIR Project. Jürgen Henschel FAIR Project Leader / Technical Director GSI & FAIR Status of the FAIR Project Jürgen Henschel FAIR Project Leader / Technical Director GSI & FAIR Finland France Germany India Poland Romania Russia Slovenia Sweden UK FAIR Strategic objectives FAIR phase

More information

RF Power Klystrons & 20 Year Look. R. Nelson 7/15/15

RF Power Klystrons & 20 Year Look. R. Nelson 7/15/15 RF Power Klystrons & 20 Year Look R. Nelson 7/15/15 RF Power klystrons 8 x 13 kw klystrons Page 2 Why A klystron? Best (only) choice at the time - 1988 Easy to use: Input (drive), output (to CM), power

More information

Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi)

Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi) Commissioning of Accelerators Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi) www.europeanspallationsource.se 6 July, 2017 Contents General points Definition of Commissioning

More information

Preparations for Installation, Testing and Commissioning based on Experience at CERN, SNS and Siemens

Preparations for Installation, Testing and Commissioning based on Experience at CERN, SNS and Siemens Preparations for Installation, Testing and Commissioning based on Experience at CERN, SNS and Siemens Eugène Tanke FRIB / MSU ESS Seminar, Lund, 6 March 2013 Outline Project Goal for the Accelerator Path

More information

A Facility for Accelerator Physics and Test Beam Experiments

A Facility for Accelerator Physics and Test Beam Experiments A Facility for Accelerator Physics and Test Beam Experiments U.S. Department of Energy Review Roger Erickson for the FACET Design Team February 20, 2008 SLAC Overview with FACET FACET consists of four

More information

A Cathode Development Cornell Cultera This scope includes all labor and purchases required produce photocathodes required by CBETA.

A Cathode Development Cornell Cultera This scope includes all labor and purchases required produce photocathodes required by CBETA. A1.01 PROJECT MANAGEMENT BNL/Cornell Michnoff A1.01.01 Milestones BNL/Cornell Michnoff This scope is a placeholder for all project high level milestones for NYSERDA. There is no cost or labor related to

More information

Status of the X-ray FEL control system at SPring-8

Status of the X-ray FEL control system at SPring-8 Status of the X-ray FEL control system at SPring-8 T.Fukui 1, T.Hirono 2, N.Hosoda 1, M.Ishii 2, M.Kitamura 1 H.Maesaka 1,T.Masuda 2, T.Matsushita 2, T.Ohata 2, Y.Otake 1, K.Shirasawa 1,M.Takeuchi 2, R.Tanaka

More information

Next Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack

Next Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack The Four 50 MW XL4 X-band klystrons installed on the 8-Pack The Demonstrate an NLC power source Two Phases: 8-Pack Phase-1 (current): Multi-moded SLED II power compression Produce NLC baseline power: 475

More information

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team Status of SOLARIS Paweł Borowiec On behalf of Solaris Team e-mail: pawel.borowiec@uj.edu.pl XX ESLS-RF Meeting, Villingen 16-17.11.2016 Outline 1. Timeline 2. Injector 3. Storage ring 16-17.11.2016 XX

More information

SPEAR 3: Operations Update and Impact of Top-Off Injection

SPEAR 3: Operations Update and Impact of Top-Off Injection SPEAR 3: Operations Update and Impact of Top-Off Injection R. Hettel for the SSRL ASD 2005 SSRL Users Meeting October 18, 2005 SPEAR 3 Operations Update and Development Plans Highlights of 2005 SPEAR 3

More information

Introduction: CW SRF linac types, requirements and challenges High power RF system architecture

Introduction: CW SRF linac types, requirements and challenges High power RF system architecture RF systems for CW SRF linacs S. Belomestnykh Cornell University Laboratory for Elementary-Particle Physics LINAC08, Victoria, Canada October 1, 2008 Outline L band Introduction: CW SRF linac types, requirements

More information

THE NEXT LINEAR COLLIDER TEST ACCELERATOR: STATUS AND RESULTS * Abstract

THE NEXT LINEAR COLLIDER TEST ACCELERATOR: STATUS AND RESULTS * Abstract SLAC PUB 7246 June 996 THE NEXT LINEAR COLLIDER TEST ACCELERATOR: STATUS AND RESULTS * Ronald D. Ruth, SLAC, Stanford, CA, USA Abstract At SLAC, we are pursuing the design of a Next Linear Collider (NLC)

More information

ANKA RF System - Upgrade Strategies

ANKA RF System - Upgrade Strategies ANKA RF System - Upgrade Strategies Vitali Judin ANKA Synchrotron Radiation Facility 2014-09 - 17 KIT University of the State Baden-Wuerttemberg and National Laboratory of the Helmholtz Association www.kit.edu

More information

CEBAF 12GeV Commissioning: Status and Plans

CEBAF 12GeV Commissioning: Status and Plans CEBAF 12GeV Commissioning: Status and Plans Arne Freyberger Dept. Accelerator Division JLAB Talk Outline 1 The Past Timeline Hot Check Out Cryogenics ACC-I & ACC-II Plan, Goals and Accomplishments 2 Lessons

More information

The LEP Superconducting RF System

The LEP Superconducting RF System The LEP Superconducting RF System K. Hübner* for the LEP RF Group CERN The basic components and the layout of the LEP rf system for the year 2000 are presented. The superconducting system consisted of

More information

PEP II STATUS AND PLANS *

PEP II STATUS AND PLANS * PEP II STATUS AND PLANS * John T. Seeman + Stanford Linear Accelerator Center, Stanford University, Stanford, CA 94309 USA The PEP II B-Factory 1 project is an e + e - colliding beam storage ring complex

More information

RF considerations for SwissFEL

RF considerations for SwissFEL RF considerations for H. Fitze in behalf of the PSI RF group Workshop on Compact X-Ray Free Electron Lasers 19.-21. July 2010, Shanghai Agenda Introduction RF-Gun Development C-band development Summary

More information

Proton Engineering Frontier Project

Proton Engineering Frontier Project Proton Engineering Frontier Project OECD Nuclear Energy Agency Fifth International Workshop on the Utilisation and Reliability of High Power Proton Accelerators (HPPA5) (6-9 May 2007, Mol, Belgium) Yong-Sub

More information

Welcome and FRIB Project Status. FRIB Highlights and Plan Ahead

Welcome and FRIB Project Status. FRIB Highlights and Plan Ahead Welcome and FRIB Project Status Thomas Glasmacher Project Manager This material is based upon work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC0000661.

More information

Detailed Design Report

Detailed Design Report Detailed Design Report Chapter 4 MAX IV Injector 4.6. Acceleration MAX IV Facility CHAPTER 4.6. ACCELERATION 1(10) 4.6. Acceleration 4.6. Acceleration...2 4.6.1. RF Units... 2 4.6.2. Accelerator Units...

More information

Status of Elettra, top-up and other upgrades

Status of Elettra, top-up and other upgrades Status of Elettra, top-up and other upgrades Emanuel Karantzoulis ELETTRA / Trieste, Italy / 2010 November 25-26 Past and Present Configurations 1994-2007 From 2008 No full energy injection Full energy

More information

Meeting the Challenge of a Difficult Job Speciality Contractor ACE Awards

Meeting the Challenge of a Difficult Job Speciality Contractor ACE Awards 1 Category 2: Meeting the Challenge of a Contractor: Kenny Electric Project Name: Comcast Denver Facility Upgrade No Commercial Breaks Comcast of Denver is the national hub for television and Internet

More information

!"!3

!!3 Abstract A single-mode 500 MHz superconducting cavity cryomodule has been developed at Cornell for the electronpositron collider/synchrotron light source CESR. The Cornell B-cell cavity belongs to the

More information

The SPEAR 3 Upgrade Project Close-out Report April 2004

The SPEAR 3 Upgrade Project Close-out Report April 2004 The SPEAR 3 Upgrade Project Close-out Report April 2004-1 - The SPEAR 3 Project 1. The Beginning Project Plan and Approval 2. The Project Start Design and Fabrication Progress 2.10 CY 1999 2.20 CY 2000

More information

Linac3 experience for LHC ion runs

Linac3 experience for LHC ion runs Linac3 experience for LHC ion runs G Bellodi for the Linac3 team Keywords: beam performance reliability set up time results of MDs remaining unknowns 1 A year in perspective Source removed: change of main

More information

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR Proceedings of FEL213, New York, NY, USA STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR F. Loehl, J. Alex, H. Blumer, M. Bopp, H. Braun, A. Citterio, U. Ellenberger, H. Fitze, H. Joehri, T. Kleeb, L.

More information

CD 0.4 Damping Ring. LBL / SLAC collaboration. M. Ross April 25, M. Ross. J. Corlett. J. Rasson. K. Jobe R&D. J. Corlett

CD 0.4 Damping Ring. LBL / SLAC collaboration. M. Ross April 25, M. Ross. J. Corlett. J. Rasson. K. Jobe R&D. J. Corlett CD 0.4 Damping Ring M. Ross J. Corlett J. Rasson B. McKee D. Atkinson Project/ Systems S. Marks R. Rimmer K. Kennedy Engineering/R&D K. Jobe R&D J. Corlett Accelerator Physics G. Koehler N. Hartman

More information

The ESS Accelerator. For Norwegian Industry and Research. Oslo, 24 Sept Håkan Danared Deputy Head Accelerator Division Group Leader Beam Physics

The ESS Accelerator. For Norwegian Industry and Research. Oslo, 24 Sept Håkan Danared Deputy Head Accelerator Division Group Leader Beam Physics The ESS Accelerator For Norwegian Industry and Research Oslo, 24 Sept 2013 Håkan Danared Deputy Head Accelerator Division Group Leader Beam Physics The Hadron Intensity Frontier Courtesy of M. Seidel (PSI)

More information

P. Adamson, Fermi National Accelerator Laboratory, Batavia, IL 60510, USA. Abstract

P. Adamson, Fermi National Accelerator Laboratory, Batavia, IL 60510, USA. Abstract Abstract 7 0 0 k W M A I N I N J E C T O R O P E R A T I O N S F O R N O νa AT FNAL P. Adamson, Fermi National Accelerator Laboratory, Batavia, IL 60510, USA Following a successful career as an antiproton

More information

CBETA Quarterly Report 7

CBETA Quarterly Report 7 Submission date: 15 September 2018 CBETA Quarterly Report 7 Project Director (BNL): Steve Peggs Peggs@bnl.gov Project Manager (BNL): Rob Michnoff Michnoff@bnl.gov Project Manager (Cornell): Karl Smolenski

More information

An Operational Diagnostic Complement for Positrons at CEBAF/JLab

An Operational Diagnostic Complement for Positrons at CEBAF/JLab An Operational Diagnostic Complement for Positrons at CEBAF/JLab Michael Tiefenback JLab, CASA International Workshop on Physics with Positrons at Jefferson Lab 12-15 September 2017 Operating CEBAF with

More information

LASER REGISTRATION FORM (LS-1)

LASER REGISTRATION FORM (LS-1) Appendix 1 LASER REGISTRATION FORM (LS-1) LASER REGISTRATION FORM (LS-1) Laser Ref. No: Supervisor Training Example Policy Note: This form is to be completed and a copy sent to the Departmental Laser Supervisor,

More information

The Construction Status of CSNS Linac

The Construction Status of CSNS Linac The Construction Status of CSNS Linac Sheng Wang Dongguan branch, Institute of High Energy Physics, CAS Sep.2, 2014, Geneva Outline The introduction to CSNS accelerators The commissoning of ion source

More information

The FAIR plinac RF Systems

The FAIR plinac RF Systems The FAIR plinac RF Systems Libera Workshop Sep. 2011 Gerald Schreiber Gerald Schreiber, GSI RF Department 2 (1) Overview GSI / FAIR (2) FAIR Proton Linear Accelerator "plinac" (3) plinac RF Systems (4)

More information

Liquid Chromatography- Mass Spectrometer Manual

Liquid Chromatography- Mass Spectrometer Manual Liquid Chromatography- Mass Spectrometer Manual Joshua Willis, Elizabeth Sattely Department of Chemical Engineering Stanford University November 6, 2014 Abstract This manual will explain the LC/MS, its

More information

The Elettra Storage Ring and Top-Up Operation

The Elettra Storage Ring and Top-Up Operation The Elettra Storage Ring and Top-Up Operation Emanuel Karantzoulis Past and Present Configurations 1994-2007 From 2008 5000 hours /year to the users 2010: Operations transition year Decay mode, 2 GeV (340mA)

More information

PEP II Status and Plans

PEP II Status and Plans SLAC-PUB-6854 September 1998 PEP II Status and Plans By John T. Seeman Invited talk presented at the 16th IEEE Particle Accelerator Conference (PAC 95) and International Conference on High Energy Accelerators,

More information

Approved by: / / R. Battaglia 12/16/2016

Approved by: / / R. Battaglia 12/16/2016 Fabrication Laboratory Revision: H Rev Date: 12/16/16 Approved by: Process Engineer / / R. Battaglia 12/16/2016 Equipment Engineer 1 SCOPE The purpose of this document is to detail the use of the Varian

More information

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting Status of BESSY II and berlinpro Wolfgang Anders Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting 16.-17.11.2016 at PSI Outline BESSY II Problems with circulators Landau cavity

More information

News from HZB / BESSY Wolfgang Anders at ESLS-RF Meeting September 2010 Trieste

News from HZB / BESSY Wolfgang Anders at ESLS-RF Meeting September 2010 Trieste News from HZB / BESSY Wolfgang Anders at ESLS-RF Meeting September 2010 Trieste Outline Status Klystrons / IOT Modifications of transmitters New LINAC for BESSY II Status BERLinPro HoBiCaT Extension --

More information

XFEL High Power RF System Recent Developments

XFEL High Power RF System Recent Developments XFEL High Power RF System Recent Developments for the XFEL RF Group Outline XFEL RF System Requirements Overview Basic Layout RF System Main Components Multibeam Klystrons Modulator RF Waveguide Distribution

More information

The PEFP 20-MeV Proton Linear Accelerator

The PEFP 20-MeV Proton Linear Accelerator Journal of the Korean Physical Society, Vol. 52, No. 3, March 2008, pp. 721726 Review Articles The PEFP 20-MeV Proton Linear Accelerator Y. S. Cho, H. J. Kwon, J. H. Jang, H. S. Kim, K. T. Seol, D. I.

More information

Full IEFC workshop Feb.

Full IEFC workshop Feb. How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix How does one keep a 50 51 year old running for another 25 years? accelerator How

More information

TTF / VUV-FEL. Schedule 2005 and Project Management Issues. Schedule 2005 Project Organisation Budget & Controlling

TTF / VUV-FEL. Schedule 2005 and Project Management Issues. Schedule 2005 Project Organisation Budget & Controlling TTF / VUV-FEL Schedule 200 and Project Management Issues Schedule 200 Project Organisation Budget & Controlling Hans Weise / DESY DESY MAC Meeting November 9th, 2004 TTF Linac Start-up After Final Installation

More information

Nick Walker DESY MAC

Nick Walker DESY MAC Nick Walker DESY MAC 4.5.2006 XFEL X-Ray Free-Electron Laser DESY ILC Project Group Accelerator Experimentation Behnke, Elsen, Walker (chair) WP 15, 16 WP 4-7 Accelerator Physics and Design WP 6 High Gradient

More information

BBU threshold current study for 6 GeV beam in 12 GeV beamline setup

BBU threshold current study for 6 GeV beam in 12 GeV beamline setup BBU threshold current study for 6 GeV beam in 12 GeV beamline setup Ilkyoung Shin and Byung C. Yunn JLAB-TN-09-004 January 12, 2009 1. Introduction The study of BBU threshold current is done for a 6 GeV

More information

HPS Slow Controls Overview

HPS Slow Controls Overview HPS Slow Controls Overview Hovanes Egiyan 6/18/2014 Hovanes Egiyan HPS Collaboration Meeting 1 Content Introduction HPS SVT Controls ECAL Controls Hall B controls Summary 6/18/2014 Hovanes Egiyan HPS Collaboration

More information

Summary of CBETA Independent Cost Reviews. R. Michnoff January 19, 2017

Summary of CBETA Independent Cost Reviews. R. Michnoff January 19, 2017 Summary of CBETA Independent Cost Reviews R. Michnoff January 19, 2017 Overview On January 18 th and 19 th, 2017, independent cost reviews were conducted by phone between BNL and Cornell University for

More information

Accelerator Instrumentation RD. Monday, July 14, 2003 Marc Ross

Accelerator Instrumentation RD. Monday, July 14, 2003 Marc Ross Monday, Marc Ross Linear Collider RD Most RD funds address the most serious cost driver energy The most serious impact of the late technology choice is the failure to adequately address luminosity RD issues

More information

TECHNICAL SPECIFICATION Multi-beam S-band Klystron type BT267

TECHNICAL SPECIFICATION Multi-beam S-band Klystron type BT267 TECHNICAL SPECIFICATION Multi-beam S-band Klystron type BT267 The company was created for the development and manufacture of precision microwave vacuum-electron-tube devices (VETD). The main product areas

More information

An Overview of Beam Diagnostic and Control Systems for AREAL Linac

An Overview of Beam Diagnostic and Control Systems for AREAL Linac An Overview of Beam Diagnostic and Control Systems for AREAL Linac Presenter G. Amatuni Ultrafast Beams and Applications 04-07 July 2017, CANDLE, Armenia Contents: 1. Current status of existing diagnostic

More information

Station-100. From its Definition to its Realization both in the Tunnel and Outside. 05/05/05 Catherine LeCocq STA

Station-100. From its Definition to its Realization both in the Tunnel and Outside. 05/05/05 Catherine LeCocq STA Station-100 From its Definition to its Realization both in the Tunnel and Outside Definition The 2 mile SLAC linac is actually 10000 ft. It was designed with a downward slope heading eastward. In its middle,

More information

What can be learned from HERA Experience for ILC Availability

What can be learned from HERA Experience for ILC Availability What can be learned from HERA Experience for ILC Availability August 17, 2005 F. Willeke, DESY HERA Performance Critical Design Decisions What could be avoided if HERA would have to be built again? HERA

More information

ANKA Status Report. N.Smale, on behalf of all ANKA colleagues, Directors : A.-S. Müller, C Heske, T Baumbach.

ANKA Status Report. N.Smale, on behalf of all ANKA colleagues, Directors : A.-S. Müller, C Heske, T Baumbach. ANKA Status Report N.Smale, on behalf of all ANKA colleagues, Directors : A.-S. Müller, C Heske, T Baumbach. Institute for Synchrotron Radiation KIT - University of the State of Baden-Wuerttemberg and

More information

ARES Status 2004(JFY)

ARES Status 2004(JFY) ARES Status 2004(JFY) Tetsuo Abe for KEKB-RF/ARES-cavity group High Energy Accelerator Research Organization (KEK) Outline 1. Fundamentals of the ARES-cavity system 2. Operation status 3. D04C/ARES multipactoring

More information

Present Status and Future Upgrade of KEKB Injector Linac

Present Status and Future Upgrade of KEKB Injector Linac Present Status and Future Upgrade of KEKB Injector Linac Kazuro Furukawa, for e /e + Linac Group Present Status Upgrade in the Near Future R&D towards SuperKEKB 1 Machine Features Present Status and Future

More information

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

Diamond RF Status (RF Activities at Daresbury) Mike Dykes Diamond RF Status (RF Activities at Daresbury) Mike Dykes ASTeC What is it? What does it do? Diamond Status Linac Booster RF Storage Ring RF Summary Content ASTeC ASTeC was formed in 2001 as a centre of

More information

EUROFEL-Report-2007-DS EUROPEAN FEL Design Study

EUROFEL-Report-2007-DS EUROPEAN FEL Design Study EUROFEL-Report-2007-DS4-095 EUROPEAN FEL Design Study Deliverable N : D 4.3 Deliverable Title: Task: Authors: Generation of 3rd harmonic photons at 90 nm DS-4 see next page Contract N : 011935 Project

More information

Accelerator Controls Part2: CERN central timing system

Accelerator Controls Part2: CERN central timing system Accelerator Controls Part2: CERN central timing system CAS 2009@Divonne Hermann Schmickler Outline Part 2 Requested Functionality of the CERN timing system Implementation: Hardware Details Software Details:

More information

PHI 5000 VersaProbe TM Operator s Guide

PHI 5000 VersaProbe TM Operator s Guide PHI 5000 VersaProbe TM Operator s Guide Part No. 705921 Rev. A Copyright 2006 ULVAC-PHI, INC. 370 Enzo, Chigasaki, JAPAN The PHI logo ( ) is a registered trademark of ULVAC-PHI, INC. Physical Electronics,

More information

ESS: The Machine. Bucharest, 24 April Håkan Danared Deputy Head Accelerator Division. H. Danared Industry & Partner Days Bucharest Page 1

ESS: The Machine. Bucharest, 24 April Håkan Danared Deputy Head Accelerator Division. H. Danared Industry & Partner Days Bucharest Page 1 ESS: The Machine Bucharest, 24 April 2014 Håkan Danared Deputy Head Accelerator Division H. Danared Industry & Partner Days Bucharest Page 1 2025 ESS construction complete 2009 Decision: ESS will be built

More information

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala) 2 Work Package and Work Unit descriptions 2.8 WP8: RF Systems (R. Ruber, Uppsala) The RF systems work package (WP) addresses the design and development of the RF power generation, control and distribution

More information

Rewrite of content supplied by client

Rewrite of content supplied by client Rewrite of content supplied by client Page: Residential Services Bringing audio and video to one room or every room in your home Whether you want a single flat screen installed on a wall or a complete

More information

Supply Connection Plans of the PANDA Cluster- Jet Target, Beam Dump and its Interface with other Modules

Supply Connection Plans of the PANDA Cluster- Jet Target, Beam Dump and its Interface with other Modules Supply Connection Plans of the PANDA Cluster- Jet Target, Beam Dump and its Interface with other Modules MEC session 14.12.2017 GSI Darmstadt Benjamin Hetz WWU Münster Institut für Kernphysik WWU Münster

More information

Advanced Photon Source - Upgrades and Improvements

Advanced Photon Source - Upgrades and Improvements Advanced Photon Source - Upgrades and Improvements Horst W. Friedsam, Jaromir M. Penicka Argonne National Laboratory, Argonne, Illinois, USA 1. INTRODUCTION The APS has been operational since 1995. Recently

More information

Kratos AXIS Ultra DLD X-ray Photoelectron Spectrometer Instructions

Kratos AXIS Ultra DLD X-ray Photoelectron Spectrometer Instructions Kratos AXIS Ultra DLD X-ray Photoelectron Spectrometer Instructions Note: Enter your complete name, CMRF user code, and date into the record book. You must have previously filled out a project information

More information

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY A. Wheelhouse ASTeC, STFC Daresbury Laboratory ESLS XVIII Workshop, ELLETRA 25 th 26 th November 2010 Contents Brief Description ALICE

More information

Status of RF Power and Acceleration of the MAX IV - LINAC

Status of RF Power and Acceleration of the MAX IV - LINAC Status of RF Power and Acceleration of the MAX IV - LINAC Dionis Kumbaro ESLS RF Workshop 2015 MAX IV Laboratory A National Laboratory for synchrotron radiation at Lunds University 1981 MAX-lab is formed

More information